DECEMBER 2025
QUARTERLY ACTIVITIES REPORT
Exceptionally well supported capital raise gave Coda the funding to commence
critical PFS level drilling
HIGHLIGHTS
Elizabeth Creek – Copper-Silver Project (South Australia)
- The Company's primary focus through 2026 remains delivery of the Elizabeth Creek Pre-
Feasibility Study (PFS).
- Major drilling programme commenced during the quarter, with approximately 70% of the
planned 6,000-7,000 metres completed by the end of December 2025.
- The programme is designed to provide representative samples for geotechnical and
metallurgical test work to support the PFS, and to underpin re-estimation of the Emmie Bluff
Mineral Resource.
- Progress on the PFS during the quarter included the appointment of an experienced Study
Manager and the engagement of specialist consultants across key technical disciplines to
support delivery of the study.
Corporate
- $11.25 million in cash on hand as at 31 December 2025.
- Entitlement Offer and institutional placements completed during the quarter, raising
$12.33 million (before costs), including a 1-for-4 issue of options.
Upcoming Work Programmes
- Drilling on site to be completed with staged demobilisation and rehabilitation to be completed
in early February.
- Commencement of water bore drilling in the March quarter, alongside metallurgical
variability testwork and geotechnical studies in support of the PFS.
- Results from drilling, metallurgical and geotechnical programmes are expected to support
progressive technical updates during the March quarter.
ASX RELEASE
30 January 2026
ASX Code: COD
CONTENTS
1.0 Overview
2.0 Projects & Assets
2.1 Tenement
Schedule
2.2 Elizabeth Creek
Copper Project
Update
2.3 Future Work
Programme
3 Corporate
3.1 Finance &
Use of Funds
4 Events
Subsequent to
Quarter End
5 Appendix 1
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
1. Overview
Discussing the quarter, Coda Minerals Chair, Keith Jones, said: “The December quarter was a period of substantial activity
for Coda. Early in the quarter the Company completed a well-supported capital raising of more than A$12 million to fund
the Elizabeth Creek Pre-Feasibility Study (PFS).
“During the period Coda commenced its largest drill programme at Elizabeth Creek since 2022. The programme is focused
on delivering the geological, metallurgical and geotechnical data required to support the PFS, which will remain the
Company’s principal activity through 2026.
“The quarter also coincided with a marked strengthening in the prices of the project’s key commodities. Copper prices
moved above US$13,000/t and silver approached US$100/oz during the period, firmly exceeding this level immediately
subsequent to quarter end. These market conditions reinforce the importance of progressing the PFS in a disciplined
manner, ensuring that development options are evaluated against a materially stronger pricing environment while
maintaining conservative technical and economic assumptions.
“The current drilling campaign represents a major step in defining the mining and processing parameters that will
underpin the PFS. To support this work, the Company has strengthened its technical capability with additional experience
in project management, mining engineering and metallurgy.
“Over the coming months, drill core from the programme will be processed through assay, metallurgical and geotechnical
laboratories in Australia and overseas. Consistent with the Company’s most recent drilling and PFS update, the March
quarter is expected to deliver a steady flow of results, including assay outcomes from the late-2025 drilling,
commencement of metallurgical variability test work and early geotechnical inputs. These workstreams are expected to
inform progressive technical updates through Q1 2026 as the Company advances the PFS in a staged and methodical
manner.”
Figure 1: PFS drilling at Emmie Bluff
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
2. Projects & Assets
2.1 Tenement Schedule
In accordance with ASX Listing Rule 5.3.3, Coda provides the following information about its tenements for the quarter ended 30 September 2025.
Table 1 Coda tenement schedule
Tenement Project Location Application Date Grant Date Expiry Date
Area
km2 Ownership
EL 6141 Elizabeth Creek SA 29 October 2017 28 October 2028 47 100% Tenements are held in a 70:30 split between Coda
Minerals and Torrens Mining Ltd, a wholly owned
subsidiary of Coda Minerals, resulting in effective
100% control by Coda Minerals.
EL 6518 Elizabeth Creek SA 25 March 2020 24 March 20251 363 100%
EL 6265 Elizabeth Creek SA 7 October 2018 6 October 2029 291 100%
EL 6945 Elizabeth Creek2 SA 17 October 2023 16 October 2029 73 100% Held 100% by Coda Minerals.
EPM 27042 Cameron River Queensland 10 October 2019 9 October 2029 22.4 100% Coda recently completed formal transfer of 100%
of the Cameron River project.
EPM 27053 Cameron River Queensland 14 February 2020 13 February 2030 12.8 100%
EL 6962 Kinloch SA 7 December 2023 6 December 2029 854 25% Held in a 25:75 split with Boss Energy. Coda has
100% base metals rights for the ground.
EL 6963 Kinloch SA 13 December 2023 12 December 2029 990 25%
EL 6964 Kinloch SA 18 December 2023 17 December 2029 555 25%
EL 6965 Kinloch SA 18 December 2023 17 December 2029 785 25%
1
A renewal application for EL 6518 was lodged with the SA DEM on the 5th
of February 2025, in line with standard renewal procedures. All tenement obligations have been met, and the Company anticipates renewal
will be authorised in the coming weeks.
2
Tenure is adjacent to Elizabeth Creek but has not been formally integrated into the broader Elizabeth Creek Project.
ELIZABETH
CREEK
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
2.2 Elizabeth Creek Project
Elizabeth Creek PFS Drill Programme3
During the December Quarter, Coda commenced a substantial, three-rig diamond drill programme anticipated
to consist of 19 drillholes for approximately 6,000-7,000m of drilling covering all major sediment-hosted copper
deposits at Elizabeth Creek. As at the end of the December quarter, the programme was approximately 70
percent complete, with drilling concluded at the MG14 and Windabout deposits, with a further six of the planned
12 holes completed at Emmie Bluff and two of the remaining holes well advanced. Results to the end of the
quarter are summarised as Table 2 and Table 3, below.
Table 2 Summary of ongoing drill programme status.
Deposit Planned Planned Metres Completed In-Progress Pending Percentage Completed
Drillholes (Approx.) Drillholes Drillholes Drillholes (Approx.)
Emmie Bluff 12 5600 6 2 4 65%
MG14 2 120 2 0 0 100%
Windabout 4 450 0 1 3 100%
Cattle Grid South 1 100 0 0 1 0%
Table 3 Drillhole collar data and Tapley intercepts(downhole4) in completed holes to date
Hole ID Prospect Easting Northing RL Planned Depth Dip Azimuth Status Tapley Intercept Actual Depth
DD25EB0041 Emmie Bluff 704448 6556505 180 430 -75 30 Completed 18.3m from 383.4 420.4m
DD25EB0042 Emmie Bluff 704465 6557137 147 436 -75 135 Completed 30.7m from 380.7 429.4m
DD25EB00435
Emmie Bluff 706394 6557019 161 480 -80 315 Completed - 440.24m
DD25EB0044 Emmie Bluff 706035 6555310 162 450 -70 330 Completed 20.3m from 424.05 465.38m
DD25EB00456
Emmie Bluff 706749 6557189 174 520 -75 270 Completed - 495.37m
DD25EB0046 Emmie Bluff 706512 6555271 168 440 -80 270 Completed 4.8m from 417.05 441.5m
DD25EB0047A Emmie Bluff 706307 6555776 161 480 -70 130 In Progress
DD25EB0048 Emmie Bluff 706293 6556351 169 480 -75 270 In Progress
DD26EB0049 Emmie Bluff 705240 6556210 168 440 -70 190 In Progress
DD25MG140001 MG14 704820 6520300 84 60 -70 90 Completed 5.7m from 29.1m 60m
DD25MG140002 MG14 704350 6520275 87 60 -70 270 Completed 9.4m from 29.5m 55.5m
DD25WIND0001A Windabout 702160 6525760 95 100 -70 270 Completed 12.8m from 76.4m 96m
DD25WIND0002 Windabout 703415 6525485 105 100 -70 270 Completed 17.6m from 79.4m 126.2m
DD25WIND0003 Windabout 702750 6525090 104 100 -70 90 Completed 23.8m from 68.9m 121.78m
DD25WIND0004 Windabout 703200 6524670 107 100 -70 90 Completed 9.9m from 61m 100.7m
Drilling has continued subsequent to the Christmas break. As of the last material announcement, Coda
anticipated the programme would conclude at approximately the end of January 2026, and remains on track to
achieve that timeline.
Elizabeth Creek PFS: Other
Work continued during the quarter to advance the Elizabeth Creek PFS. The company appointed an experienced
Study Manager and a number of subject matter experts to assist in specific technical areas.
3
This section is adapted from an ASX announcement released 12 January 2025 entitled “Elizabeth Creek Copper-Silver Drilling
Recommences in 2026”. Please see here for full details including JORC Table 1: https://codaminerals.com/announcements/7323990
4
See Table 3, Appendix 2 for true widths.
5
Hole abandoned due to challenging drilling conditions
6
Hole achieved target depths on the northwestern edge of the resource but did not intercept Tapley Hill Formation black shale.
ELIZABETH
CREEK
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
3. Corporate
3.1 Finance & Use of Funds
Pursuant to ASX Listing Rule 5.3.2, the Company confirms that there were no mining production and
development activities during the quarter by the Company.
The Company incurred total cash outflow from operating activities of $3.02 million for the quarter ended 31
December 2025. This included extensive drilling and site costs of $2.42 million in exploration and evaluation
expenditure as the Company moves activities forward towards completing its pre-feasibility study. The quarterly
corporate costs included year end compliance costs for the annual report and AGM, travel and associated
investor relations costs for conferences and payment of GST for drilling costs that has been recovered post 31
December 2025. The total administration costs for the quarter were $0.42 million. Coda received $49k in
additional to interest on cash balances during the quarter.
During the quarter ended 31 December 2025, a total of $185k was paid to the Directors of the Company as
remuneration including a payment of 50% of the fees in cash to non-executive director for the period 1 July to
30 September 2025. Please refer to Section 6.1 of the Appendix 5B below.
On 27 October 2025, the Company announced the completion of a capital raising for $12.33 million (before
costs) through an Entitlement Offer to existing shareholders and a placement to institutional and sophisticated
investors, both of which were oversubscribed. The Company issued 83,318,319 fully paid ordinary shares at
$0.10 for the Entitlement Offer and a further 38,095,239 fully paid ordinary shares at $0.105 to institutional and
sophisticated investors. The Entitlement offer and the placement included the issue of 1 option for every 4
shares subscribed in addition to the issue of options to lead manager and underwriters for services rendered.
The total number of options issued was 63,683,316. The options have an exercise price of $0.15 per option and
expire on 28 March 2029.
After receiving shareholder approval at the Company’s annual general meeting, the Company issued 10 million
performance rights to the CEO and executive director which include a number of performance hurdles including
share price and operational targets.
The Company issued 250,046 fully paid ordinary shares to non-executive directors in lieu of directors fees to
settle the remaining unpaid balance of the 30 June 2025 directors’ fee.
The Company issued a further 400,000 fully paid ordinary shares at an issue price of $0.075 pursuant to an
investor relations agreement with Cumulus Wealth Pty Ltd as part of the on-going corporate advisory support.
The Company ended the quarter with $11.25 million in cash and cash equivalents after completing the first
phase of the drilling programme at the Company’s flagship Elizabeth Creek project and has a strong cash position
available to progress the Elizabeth Creek pre-feasibility study.
4. Events Subsequent to Quarter-End
Drilling ceased over the Christmas break at Elizabeth Creek and recommenced in January of 2026. Drilling has
continued at a good pace and the Company remains on track to conclude the majority of drilling operations in
the coming days, via a staged demobilisation.
Planning has continued for the next round of drilling, which will consist of two sets of production and monitoring
bores to begin assessment of groundwater potential and exploration for sufficient water for the project’s needs.
This drilling is currently planned to commence in March.
Other anticipated work programmes during the quarter include metallurgical and geotechnical testwork in
support of mining and processing trade-off studies and final selections.
ELIZABETH
CREEK
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
This announcement has been authorised for release by the Board of Coda Minerals Ltd
Further Information:
Chris Stevens
Chief Executive Officer
Coda Minerals Limited
info@codaminerals.com
Media:
Nicholas Read
Read Corporate
nicholas@readcorporate.com.au
ELIZABETH
CREEK
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
5. Appendix 1
5.1 Elizabeth Creek Mineral Resources
Table 4 Aggregated Mineral Resources at Elizabeth Creek
OPEN PIT Proposed Tonnage Cut-off Copper Cobalt Silver Zinc Copper Equivalent
Resource Category Type Mining Mt Grade Grade Contained Grade Contained Grade Contained Grade Contained Grade Contained
Method (% Cu) Metal (t) (ppm Co) Metal (t) (g/t Ag) Metal (Moz) (ppm Zn) Metal (t) (% CuEq) Metal (t)
MG14 Indicated Zambian Open Pit 1.8 0.5% CuEq 1.2% 22,700 330 600 14 0.8 1.7% 30,600
Cattle Grid South Inferred Breccia Open Pit 5.8 0.2% Cu 0.6% 36,000 120 700 3.5 0.7 684 4000 36,0007
Windabout Indicated Zambian Open Pit 17.7 0.5% CuEq 0.8% 136,100 490 8700 8 4.6 1.4% 249,100
Sub Totals Indicated Zambian Open Pit 19.5 0.5 CuEq 0.8% 158,800 480 9300 8.5 5.4 1.4% 316,000
(Open Pit) Inferred Breccia Open Pit 5.8 0.2% Cu 0.6% 36,000 120 700 3.5 1 684 4,000
UNDERGROUND Proposed Tonnage Cut-off Copper Cobalt Silver Zinc Copper Equivalent
Resource Category Type Mining Mt Grade Grade Contained Grade Contained Grade Contained Grade Contained Grade Contained
Method (% Cu) Metal (t) (ppm Co) Metal (t) (g/t Ag) Metal (Moz) (ppm Zn) Metal (t) (% CuEq) Metal (t)
Indicated Zambian Underground 37.5 1% CuEq 1.3% 485,000 590 22,000 17 20.6 1800 66000 1.9% 715,000
Emmie Bluff Inferred Zambian Underground 2.7 1% CuEq 0.9% 46,000 280 1,000 12 1.1 1700 5000 1.3% 36,000
Sub Total
(Underground)
Combined Zambian Underground 40.2 1% CuEq 1.3% 511,000 570 23,000 16.8 21.7 1700 70000 1.9% 751,000
Project Wide Total8 65.5 Mt 725,800t Contained Cu 33,000t contained Co 28 Moz Contained Ag 75,000t Contained Zn9 1,067,000t contain CuEq
7
No Copper Equivalent was calculated for Cattle Grid South. Contained CuEq tonnes quoted in this column for Cattle Grid South consist of contained copper only.
8
Total figures have been aggregated purely for convenience and to contextualise the specific contribution of individual Mineral Resource Estimates to the overall project scale. Grades reported are tonnage-weighted
averages of the individual Mineral Resource Estimates. Coda notes that the total figure includes resources reported at varying cut-off grades, with varying estimation techniques, metallurgical properties and proposed
mining methods. Individual Mineral Resource Estimates should be considered individually. A total copper equivalent figure has not been disclosed as Coda does not believe it is currently appropriate to calculate a
copper equivalent for the Cattle Grid South Mineral Resource Estimate. Please see below sections Statement Regarding Metal Equivalent Calculations and Competent Persons Statement for full details on the calculation
of copper equivalents and links to original releases/CP statements. Figures have been rounded for simplicity.
9
No Zinc estimate was provided for the MG14 and Windabout deposits. This figure reflects the contained tonnage solely from Emmie Bluff and Cattle Grid South.
ELIZABETH
CREEK
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
5.2 Competent Persons’ Statements and Confirmatory Statement - Mineral Resource
Estimates
MG14 Indicated Mineral Resource: The information is extracted from the report entitled "Confirmation
Statements JORC" created on 26th October 2020 and is available to view at:
https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-02298915-
6A1003162&v=70bc033a22188bdfefb8a0b8ad3c24897ef2837d.
The company confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcement and, in the case of estimates of Mineral Resources or Ore
Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed. The company confirms that the form
and context in which the Competent Person’s findings are presented have not been materially modified from
the original market announcement.
Windabout Indicated Mineral Resource: The information is extracted from the report entitled "Confirmation
Statements JORC" created on 26th October 2020 and is available to view at:
https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-02298915-
6A1003162&v=70bc033a22188bdfefb8a0b8ad3c24897ef2837d.
The company confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcement and, in the case of estimates of Mineral Resources or Ore
Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed. The company confirms that the form
and context in which the Competent Person’s findings are presented have not been materially modified from
the original market announcement.
Emmie Bluff Mineral Resource: The information is extracted from the report entitled “Scoping Study Update
Delivers Materially Improved Economics" created on 30 January 2024 and is available to view at:
https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-02766550-6A1191314.
The company confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcement and, in the case of estimates of Mineral Resources or Ore
Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed. The company confirms that the form
and context in which the Competent Person’s findings are presented have not been materially modified from
the original market announcement.
Cattle Grid South Mineral Resource: The information is extracted from the report entitled “Initial Copper
Resource for Cattle Grid South" created on 03 July 2024 and is available to view at:
https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-02823989-
6A1214274&v=4015c7b87631faf94ecd96975272ff9ad5cb14c3.
The company confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcement and, in the case of estimates of Mineral Resources or Ore
Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed. The company confirms that the form
and context in which the Competent Person’s findings are presented have not been materially modified from
the original market announcement.
ELIZABETH
CREEK
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
5.3 Listing Rule 5.19.2
In relation to any Production Target or any forecast financial information based on any Production Target quoted
or referenced in this announcement, the Company confirms that all material assumptions underpinning both
the Production Target and any forecast financial information continue to apply and have not materially changed.
The original ASX announcement released on 3 December 2024 relating to any Production Target or forecast
financial information derived from any Production Target referenced within this announcement can be found
here.
5.4 Listing Rule 5.23.2
The Company confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcements cited in this announcement and, in the case of estimates of
Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the
estimates in the relevant market announcement continue to apply and have not materially changed. The
Company confirms that the form and context in which the Competent Person’s findings are presented have not
been materially modified from the original market announcement.
5.5 Statement Regarding Metal Equivalent Calculations
Metal Equivalent grades are quoted for one or more of the Emmie Bluff, Windabout and MG14 Mineral
Resources, or for exploration results considered by the company to be related directly to one of these Mineral
Resources, in this announcement.
For the Emmie Bluff Mineral Resource:
The Emmie Bluff Mineral Resource is reported as 40.2Mt @ 1.27% Cu, 569 ppm Co, 16.8 g/t Ag and 0.17% Zn
(1.87% Copper Equivalent (CuEq)) reported at a cut-off grade of 1% CuEq. The calculation of this metal equivalent
is based on the following assumptions.
Metal Coefficient Forecast Price Price Unit
Copper 0.8 $7,000 USD/Tonne
Cobalt 0.85 $55,000 USD/Tonne
Zinc 0.9 $2,100 USD/Tonne
Silver 0.85 $18.50 USD/Oz
Price assumptions used when calculating copper equivalent grades were based primarily on Consensus
Economics forecasts of metals, except for Cobalt, which was sourced via communication with subject matter
experts. Metallurgical assumptions used when calculating copper equivalent grades were based on a simple bulk
float utilising rougher and minimal cleaner/scavenger circuits. The produced a reasonably consistent mean
recovery across most metals of between approximately 83 and 94 percent. For simplicity, and to in part account
for losses associated with less intensive cleaner floats and losses to the hydromet plant, these figures were
rounded down to the nearest 5%.
Application of these assumptions resulted in the following calculation of CuEq:
𝐶𝑢𝐸𝑞% = 𝐶𝑢% + 0.00068 × 𝐶𝑜 𝑝𝑝𝑚 + 0.337 × 𝑍𝑛 % + 90.3 ×
𝐴𝑔 𝑝𝑝𝑚
10000
ELIZABETH
CREEK
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
For the Windabout and MG14 Mineral Resource:
The Windabout and MG14 Mineral Resource are reported at a cut-off grade of 0.5% CuEq as:
• Windabout: 17.67Mt @ 0.77% Cu, 492 ppm Co and 8 g/t Ag (1.41% CuEq)
• MG14: 1.83Mt @ 1.24% Cu, 334 ppm Co and 14 g/t Ag (1.84% CuEq)
The calculation of this metal equivalent is based on the following assumptions.
Metal Mining
Recovery %
Dilution % Recovery % Payability % Forecast Price Price Unit
Copper 0.9 0.05 0.6 0.7 $6,600 USD/Tonne
Cobalt 0.9 0.05 0.85 0.75 $55,000 USD/Tonne
Price assumptions used when calculating copper equivalent grades were based on recent historical metal prices
at the time of calculation (2018). Metallurgical assumptions are based on extensive metallurgical testwork
undertaken on the two deposits to 2018 across various potential flowsheets involving both floatation and
leaching. Ag analyses in the estimation and metallurgical testwork were considered insufficient at the time to
include in the metal equivalent calculation.
Application of these assumptions resulted in the following calculation of CuEq:
𝐶𝑢𝐸𝑞% = 𝐶𝑢% + 0.0012 × 𝐶𝑜 𝑝𝑝𝑚
It is the opinion of the company that both sets of prices used in the calculations are reasonable to conservative
long-term forecasts for real dollar metal prices during the years most relevant to the deposits (approx. 2026-
2030).
It is the opinion of the company that all of the elements included in the metal equivalent calculations have a
reasonable potential to be recovered and sold.
For full details of the Emmie Bluff Metal Equivalent calculation, please see “Scoping Study Update Delivers
Materially Improved Economics”, released to the ASX on 30th January 2024 and available at
https://www.codaminerals.com/wp-content/uploads/2024/01/20240130_Coda_ASX-ANN_Scoping-Study-
Update-Delivers-Materially-Improved-Economics_RELEASE.pdf.
For full details of the MG14/Windabout Metal Equivalent Calculation, please see “Confirmation of Exploration
Target & Mineral Resource and Ore Reserve Statement”, released to the ASX on 23rd October 2020 and available
at https://www.codaminerals.com/wp-content/uploads/2020/10/20201026_Coda_ASX-ANN_Confirmation-
Statements-JORC.pdf.
ELIZABETH
CREEK
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
5.6 Forward Looking Statements
This announcement contains ‘forward-looking information’ that is based on the Company’s expectations, estimates
and projections as of the date on which the statements were made. This forward-looking information includes, among
other things, statements with respect to the Company’s business strategy, plans, development, objectives,
performance, outlook, growth, cash flow, projections, targets and expectations, mineral reserves and resources, results
of exploration and related expenses. Generally, this forward-looking information can be identified by the use of
forward-looking terminology such as ‘outlook’, ‘anticipate’, ‘project’, ‘target’, ‘potential’, ‘likely’, ‘believe’, ‘estimate’,
‘expect’, ‘intend’, ‘may’, ‘would’, ‘could’, ‘should’, ‘scheduled’, ‘will’, ‘plan’, ‘forecast’, ‘evolve’ and similar expressions.
Persons reading this announcement are cautioned that such statements are only predictions, and that the Company’s
actual future results or performance may be materially different. Forward-looking information is subject to known and
unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of activity,
performance or achievements to be materially different from those expressed or implied by such forward-looking
information.
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Coda Minerals Ltd
ABN Quarter ended (“current quarter”)
49 625 763 957 December 2025
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(6 months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
(a) exploration & evaluation (2,422) (2,811)
(b) development - -
(c) production - -
(d) staff costs (229) (474)
(e) administration and corporate costs (417) (752)
1.3 Dividends received (see note 3) - -
1.4 Interest received 49 83
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - 34
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(3,020) (3,919)
2. Cash flows from investing activities
2.1 Payments to acquire or for:
(a) entities - -
(b) tenements - -
(c) property, plant and equipment (9) (29)
(d) exploration & evaluation - -
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(6 months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - - -
(f) other non-current assets - - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - -
2.6 Net cash from / (used in) investing
activities
(9) (29)
3. Cash flows from financing activities
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
12,332 12,332
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(1,034) (1,034)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (Lease payment including interest) (31) (62)
3.10 Net cash from / (used in) financing
activities
11,267 11,233
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
3,011 3,964
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(3,020) (3,919)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(9) (29)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
11,267 11,233
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.