Coda Minerals AGM Presentation - November 2026
Released
Released
Announcement PDF
AGM Presentation
11 November 2026
Coda Minerals
Investor
Presentation
ASX COD
Important Notices
Nature of this document: The purpose of this presentation is to provide general information about Coda Minerals Limited (ACN 625 763 957) (the ‘Company’). Unless otherwise stated herein, the information in this
presentation is based on the Company’s own information and estimates as at the date of this presentation. In attending this presentation or viewing this document you agree to be bound by the following terms and
conditions.
Not an offer or advertisement: This presentation is for information purposes and does not constitute or form any part of any offer or invitation to sell or issue, or any solicitation of any offer to purchase or subscribe for, any
securities in the Company in any jurisdiction. This presentation and its contents must not be distributed, transmitted or viewed by an person in any jurisdiction where the distribution, transmission or viewing of this
document would be unlawful under the securities or other laws of that or any jurisdiction. In particular, this presentation may not be distributed or released, directly or indirectly, in the United States. This presentation does
not constitute an advertisement for an offer or proposed offer of shares. Neither this presentation nor anything contained in it forms the basis of any contract or commitment and it is not intended to induce or solicit any
person to enter into, or refrain from entering into, any contract or commitment.
Not financial product advice: This presentation does not take into account the individual investment objectives, financial situation and particular needs of each of the Company’s shareholders or potential investors. You may
wish to seek independent financial and taxation advice before making any decisions in respect to this presentation. Neither the Company nor any of its related bodies corporate is licensed to provide financial advice in
respect of the Company’s securities or any other financial products.
Forward-looking statements: Certain statements in the presentation are or may be perceived as “forward looking statements” and represent the Company’s intentions, projections, expectations or beliefs concerning,
among other things, future operating and exploration results or the Company’s future performance. You are cautioned not to place undue reliance on any forward looking statement. These forward looking statements are
based on current expectations at the date of this publication. The projections, estimates and beliefs contained in such forward looking statements necessarily involve known and unknown risks and uncertainties, and are
necessarily based on assumptions, which may cause the Company’s actual performance and results in future periods to differ materially from any express or implied estimates or projections.
Disclaimer: No representation or warrant, express or implied, is made by the Company that the material contained in this presentation will be achieved or prove to be correct. Except for statutory liability which cannot be
excluded, each of the Company, its directors, officers, employees, advisers, agents and contractors expressly disclaims any responsibility for the accuracy, fairness, sufficiency or completeness of the material contained in
this presentation, or any opinions or beliefs contained in this presentation, and excludes all liability whatsoever (including negligence) for any loss or damage which may be suffered by any persons as a consequence of any
information in this presentation or any error or omission there from. The Company is under no obligation to update or keep current the information contained in this presentation or to correct any inaccuracy or omission
which may become apparent, or to furnish any person with any further information. Any opinions expressed in the presentation are subject to change without notice.
Unverified information: This presentation may contain information (including information derived from publicly available sources) that has not been independently verified by the Company.
This presentation is intended to be provided to persons who are sophisticated, accredited, professional or institutional investors (as applicable) to whom securities may be offered without a prospectus or other disclosure
document, whether in Australia or any other jurisdiction, and to whom this presentation may be lawfully communicated, including investors referred to in section 708 of the Corporations Act 2001 (Cth).
Not a prospectus: This presentation is not a prospectus, product disclosure statement or other investment disclosure document, and the level of disclosure in this presentation is less that such documents. It does not
purport to contain all of the information that a prospective investor may require to make an evaluation of [short name] or its business activities. Nothing in this presentation is, or is intended to be, a recommendation to
invest in the Company. The Company does not purport to give financial or investment advice.
The photograph used on page 14 was provided by Adam Mørk Architectural Photography and is used with permission.
ASX COD
VIDEO PRESENTATION
A video presentation accompanying this pack will be available to view
online on our website.
https://codaminerals.com/
ASX COD
T H E A D D R E S S ASX:COD
This is where mines get built.
Mine locations indicative
16 km BHP Oak Dam West
40 km BHP Carrapateena
114 km BHP Olympic Dam
150 km Port Augusta port facilities, by sealed road
Copper Key electrification metal, looming supply gulf
Silver Key solar component, demand exceeding supply.
Cobalt
Upside opportunity from growing battery demand
& flowsheet reintegration.
Olympic Dam — BHP
Oak Dam West — BHP
Carrapateena — BHP
Elizabeth Creek
T H E P R O P O S I T I O N ASX:COD
A long-life copper-silver deposit to make finished metal in one plant.
T H E R E S OU R C E
706kt Cu
28Moz Ag1
• 65.5Mt @ 1.6% CuEq
• Two open pits for early
revenue
• Emmie Bluff 400m deep,
shallow by global
standards
T H E C H E MI S T RY
~95% Cu
~98% Ag2
• Extraction by whole-ore
chloride leach
• Copper cathode and silver
doré on site, no smelter
• 3.5% royalty, not 5%
T H E A D DR E S S
South
Australia
• 16km from BHP's Oak
Dam West project
• Ranked 4th globally by
Fraser Institute
• Scoping Report gazetted
T H E V A L U E
A$2.25Bn
56% IRR3
• Pre-tax NPV7 and IRR
• PFS underway to build on
Scoping Study outcomes
and refine project
economics
1Please see ASX releases on 28 July 2021, 23 August 2021, 28 February 2022, 20 June 2022, 30 January 2024 and 3 July 2024 for full details of all mineralised holes and Table 1. Please see Appendix for links to full Resource Table, Resource Statements, Confirmatory
Statements under LR 5.19.2 and Copper Equivalent grade calculations.
3Please see ASX release Elizabeth Creek Project Economics - Additional Information on 10th March 2026.
2Recoveries from Emmie Bluff deposit using chloride and air oxidative leach. For full details, please see ASX release New Flowsheet Delivers Significant Cu-Ag Economic Uplift on 28th August 2025
M IN E- L IF E P RO D U C T IO N
15.5 years3 454kt
copper
20.3Moz
silver
Cu
29
Ag
47
CORPORATE
$37M
Market Capitalisation
11 Nov 2026
427M
Ordinary Shares
11 Nov 2026
$10.08M
Cash and Equivalents
30 Sept 2026
$0.087
Share Price
10 Nov 2026
ASX COD
Keith Jones
NON-EXEC CHAIR
Robin Marshall
NON-EXEC DIRECTOR
Susan Park
COMPANY SECRETARY
Chris Stevens
CEO, DIRECTOR
Paul Hallam
NON-EXEC DIRECTOR
Matt Weber
MANAGER GEOLOGY
Colin Moorhead
STEERCO CHAIR
Heather Evans
GENERAL MANAGER
METALLURGY & PROCESS
Experienced Board & Management
Project delivery, exploration, studies and corporate
leadership.
200+
years combined
experience
25+
projects delivered
& operated
Discovery to
development
expertise
BOARD OF DIRECTORS
SENIOR MANAGEMENT
CODA’S COPPER PORTFOLIO
Resource Confidence Cut-off Mt Cu (%) Co (ppm) Ag (g/t) CuEq (%)
CuEq
Contained Metal (kt)
Emmie Bluff
93% Indicated,
7% Inferred
1.0% CuEq 40.2 1.3% 569 17 1.9% 751
MG14 Indicated 0.5% CuEq 1.8 1.2% 334 14 1.7% 31
Windabout Indicated 0.5% CuEq 17.7 0.8% 492 8 1.4% 249
Cattle Grid South Inferred 0.2% Cu 5.8 0.6% 121 4 N/A 36
Total 65.5 1.60% 1,067
1Please see ASX releases on 28 July 2021, 23 August2021, 28 February 2022, 20 June 2022, 30 January 2024 and 3 July 2024 for full details of all mineralised
holes and Table 1. Please see Appendix for links to full Resource Table, Resource Statements, Confirmatory Statements under LR 5.19.2 and Copper
Equivalent grade calculations.
JORC RESOURCE SUMMARY1
65.5Mt @ 1.6% CuEq
> 1 Million Tonnes of CuEq
EMMIE BLUFF (FLAGSHIP)
Underground Deposit
~ 400m depth
Total Area: 701 km2
ELIZABETH CREEK
OAKDEN
Cu-Co-Ag Prospect
~ 30m depth
EMMIE DEEPS
Iron Oxide Copper Gold (IOCG)
Underground Deposit
~ 800m depth
WINDABOUT
Open Pit Deposit
~ 50 - 70m depth
MG14
Open Pit Deposit
~ 20m depth
CATTLE GRID SOUTH
Open Pit Deposit
~ 30m depth
ASX:COD
ASX:COD
400m
Please see Appendix for links to full Resource Table, Resource Statements, Confirmatory Statements under LR 5.19.2 and Copper Equivalent grade calculations.
CURRENT ACTIVITIES
❖ MRE Update
❖ Mine Planning
Mine planning and updated resource work are advancing
development readiness and supporting future reserve definition.
❖ MG14 - 1.3Mt @ 1.9% CuEq Production Target
❖ WINDABOUT - 6Mt @ 1.7% CuEq Production Target
❖ Provides early revenue
❖ EMMIE BLUFF - 32Mt @ 1.8% CuEq Production
Target
❖ Simple mining via conventional drill & blast or
mechanical cutting machines
SIMPLE MINING – OPEN PIT AND 400M UNDERGROUND
WINDABOUT
MG14
EMMIE BLUFF
Open Pits
Flagship Underground
ASX:COD
BASE CASE: WHOLE-ORE CHLORIDE LEACH
ROM
JAW CRUSHER MILLING
WHOLEORE LEACH
*Extraction to leachate from Emmie Bluff deposit using chloride and air oxidative leach. For full details, please see ASX release New Flowsheet Delivers Significant Cu-Ag Economic Uplift on 28th August 2025. Capex per ASX release 10 Mar
2026. Cobalt: please see ASX release Positive Cobalt Flotation Resultsat Elizabeth Creek on 22nd October 2026
CURRENT BASE CASE
Simplified leach flowsheet delivers exceptional recoveries
(95% Cu, 98% Ag)
Cu
COPPER
CATHODE
Ag
SILVER
DORE
Zn
ZINC
CARBONATE
SX/EW
MERRILL-CROWE
PRECIPITATION
94.8%
Copper extraction
98.2%
Silver extraction
P80 75µm
grind, vs 32µm for
flotation
40%
Cobalt extraction
• Cobalt extraction currently at 40% with additional flotation upside
• One plant, one leach: near-neutral chloride solution
• Finished products on site: LME-grade cathode and silver doré
• Newer technology with exceptional suitability to Elizabeth Creek
ore type
OPTIONAL COBALT CIRCUIT Ongoing
testwork to optimize cobalt recovery
pathway from leached residue. Project
economics currently assume no revenue
from cobalt.
Co
COBALT
SULPHATE
ASX:COD
ACTIVE TRADE OFF: FLOTATION–ALBION ROUTE
ROM
JAW CRUSHER MILLING
Please see ASX release NewResources, Higher RecoveriesBoost Elizabeth Creek Value on 3rd December 2024. Flotation–Albion route per ScopingStudy updates 2023–2024.
UNDER ASSESSMENT
Ongoing flotation test work continues to assess options
to produce cobalt in addition to copper and silver
Cu
COPPER
CATHODE
Ag
SILVER
DORE
Zn
ZINC
CARBONATE
Co
COBALT
SULPHATE
SX/EW
MERRILL-CROWE
PRECIPITATION
OXIDATIVE ACID LEACH
CONCENTRATE
FLOTATION
CRYSTALLISATION
83% Cu 82% Ag 86% Co
extraction across the key metals, bulk-float
test work
• Flotation to a copper-cobalt concentrate, then an Albion oxidative leach of that concentrate
• Grind (P80 ~58µm); SX/EW and crystallisation
• Finished products on site: cathode, silver doré and a cobalt sulphate product (based on Scoping Study)
• Established technology; a smaller downstream circuit
THE PFS DECIDES on capital, operability, recovery, technical risk and cobalt. Both routes make finished metal on site.
TIER 1 LOCATION ASX:COD
What gets mines built
The technical questions get the attention BUT these are the things that stop projects.
WHAT HOLDS MINES BACK AT ELIZABETH CREEK
Approvals
Scoping Report gazetted 22 July 2026: the requirements for assessing a future Mining Lease
Application are defined. The application and approval remain ahead.
Heritage, native title and land
access
Pastoral lease, single-use ground. No major native title or landholder access issues identified to date.
Location
Next to three BHP projects: Carrapateena (operating, 40 km), Olympic Dam (operating, 114 km) and
Ankata (Oak Dam West) (developing, 16 km). This is an area where mines get built.
Sovereign risk
South Australia. Fraser Institute: ranked 4th globally. Established copper jurisdiction with a statewide
copper strategy.
Water, power and transport Stuart Highway at the front door; 150 km by sealed road to Port Augusta. Power infrastructure on site,
access to be secured. Water drilling under way; the proposed Northern Water pipeline passes the site.
Mining and processing questions remain, as they should at this stage. What we have is a project in an established mining region,
with infrastructure close by and no major land-access issues identified. That is what helps get a mine built.
Gazettal defines the assessment requirements; it is not a mining approval. Distances approximate. Power and water access are expectations, not agreements: power connection, Northern Water pipeline use and water
sufficiency are subject to studies and agreements not yet in place. Land-access statement per Company; heritage and native-title processes continue. Sources: Annual Report (9 Oct 2026); ASX release 22 Oct 2026; RRS
Gold Coast presentation (Sept 2026); Fraser Institute Annual Survey.
T H E B R I D G E · M U L T I P L E F U N D I N G O P T I O N S ASX:COD
PFS – integral to funding, silver provides options.
W HO FUN DS A CO PPE R M I NE — AND W HAT T HEY NEE D T O S EE
Streamers want a defined metal schedule —
especially silver
Banks want Ore Reserves, costs and a
schedule they can lend against
Strategics want a resource, a flowsheet and a
permitting path they can trust
Traders want a finished, saleable product
with a delivery date
The PFS answers all four
— mine plan, recoveries, costs and risks —
with independent engineers standing behind
it. It is the first document funders can act on.
Finished metal on site widens the field for
Coda: silver stream · strategic joint venture ·
offtake pre-payment · project debt.*
*No funding commitments are in place and there is no certainty any will be secured.
P F S W O R K P R O G R A M · P R O G R E S S A N D P A T H W A Y ASX:COD
A major body of work is driving the PFS forward
W O R K S T R E A M
C O M PL E T E D O N GO I N G N E XT S T EP S
Mining &
Mineral
Resources
✓ 19-hole, 6,352 m drill program
✓ 6-hole hydrogeological drill program
✓ Tailings storage facility (TSF) – Phase 1
✓ Geotechnical program
✓ LiDAR survey
✓ Flood modelling
⚫ TSF geotechnical study
⚫ Waste rock characterisation study
⚫ Resource update OP EN P IT
⚫ Detailed mine scheduling OP EN P IT
⚫ Mining method selection U N D ER G R OU N D
⚫ Mineral Resource update U N D ER G R OU N D
⚫ Mine scheduling U N D ER G R OU N D
➔ Mining method selection U N D ER G R OU N D
➔ Detailed mine planning U N D ER G R OU N D
Metallurgy &
Process
✓ First-round pre-variability testwork L EA C H
✓ Downstream processing work program L EA C H
✓ Residue flotation for cobalt recovery L EA C H
✓ METSIM modelling L EA C H
✓ Flotation optimisation study F L OT A T I ON
✓ Comminution study B OT H R OU T E S
⚫ Locked-cycle testing L EA C H
⚫ Variability testwork – detailed Phase 2 L EA C H
⚫ CAPEX / OPEX estimation – Phase 1 L EA C H
⚫ Residue flotation for cobalt – Round 2 L EA C H
⚫ Detailed variability program F L OT A T I ON
⚫ CAPEX / OPEX update F L OT A T I ON
➔ Process selection
➔ Detailed process engineering by independent
engineers
Community &
Environment
✓ Approvals Stage 1 – Scoping Report gazetted
✓ Groundwater dependent ecosystem survey
✓ Stage 1 ecology survey
⚫ EPBC self-assessment
⚫ Hydrogeological modelling
⚫ Hydrogeological pump testing
⚫ Greenhouse gas emissions estimation
⚫ Community engagement & social impact study
⚫ Detailed heritage surveys
➔ Environmental air quality survey
➔ Noise and dust survey
➔ Ecology study
➔ Soil study
➔ Regional groundwater model
➔ Water balance
➔ Mining Lease application
Commercial &
Operations
✓ Preliminary infrastructure layout
✓ Operating model trade-off and selection
⚫ Business operations support model
⚫ Workforce planning
➔ PFS detailed economic modelling
➔ PFS independent expert review
➔ PFS delivery to market
Work program as described by the Company; next steps are indicative and subject to change. TSF = tailings storage facility. EPBC = Environment Protection and Biodiversity Conservation Act 1999 (Cth). CAPEX / OPEX = capital and operating cost estimates. LEACH = whole-ore
chloride leach route; FLOTATION = flotation–Albion route.
Appendices
Coda Minerals - Sustaining Tomorrow
15
Mineral Resources and Exploration Targets
1. MG14 Indicated Mineral Resource: The information is extracted from the report entitled "Confirmation Statements JORC" created on 26th October 2020 and is available to view at: https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-
research/1.0/file/2924-02298915-6A1003162&v=70bc033a22188bdfefb8a0b8ad3c24897ef2837d. The company confirms that it is not aware of any new information or data that materially affects the information included in the original market
announcement and, in the case of estimates of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not
materially changed. The company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
2. Windabout Indicated Mineral Resource: The information is extracted from the report entitled "Confirmation Statements JORC" created on 26th October 2020 and is available to view at: https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-
research/1.0/file/2924-02298915-6A1003162&v=70bc033a22188bdfefb8a0b8ad3c24897ef2837d. The company confirms that it is not aware of any new information or data that materially affects the information included in the original market
announcement and, in the case of estimates of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not
materially changed. The company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
3. Emmie BluffMineral Resource: The information is extracted from the report entitled “Scoping Study Update Delivers Materially Improved Economics" created o n 30 January 2024 and is available to view on https://cdn-
api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-02766550-6A1191314. The company confirms that it is not aware of any new information or data that materially affects the information included in the original market
announcement and, in the case of estimates of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not
materially changed. The company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
4. Cattle Grid South Mineral Resource: The information is extracted from the report entitled “Initial Copper Resource for Cattle Grid South" created on 03 July 2024 and is available to view on https://cdn-api.markitdigital.com/apiman-
gateway/ASX/asx-research/1.0/file/2924-02823989-6A1214274&v=4015c7b87631faf94ecd96975272ff9ad5cb14c3. The company confirms that it is not aware of any new information or data that materially affects the information included in the
original market announcement and, in the case of estimates of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and
have not materially changed. The company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
Mineral Resources
APPENDIX A: STATEMENTS
Coda Minerals - Sustaining Tomorrow
16
Competent Person Statement for JORC 2012 Mineral Resources - MG14 & Windabout
This report was prepared in accordance with the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’ (“JORC Code”) by Tim Callaghan, who is a Member of the Australian Institute of Mining and
Metallurgy (“AusIMM”), has a minimum of five years’ experience in the estimation and assessment and evaluation of Mineral Resources of this style and is the competent Person as defined in the JORC Code. This announcement accurately summarises
and fairly reports his estimations and he has consented to the resource report in the form and context it appears.
The MG14 and Windabout Mineral Resource at the Elizabeth Creek Copper-Cobalt Project has been estimated by Mr Tim Callaghan, an external consultant, and is reported under the 2012 Edition of the Australasian Code for reporting of Exploration
Results, Mineral Resources and Ore Reserves (see ASX announcement 26th October 2020 titled: Confirmation Statements JORC).
Competent Person Statement for JORC 2012 Mineral Resources – Emmie Bluff
The information in this statement that relates to the Mineral Resource Estimates is based on work done by Dr Michael Cunningham of Sonny Consulting Services Pty Ltd. The information in this report which relates to exploration results is based on
information compiled by Mr. Matthew Weber, who is an employee of the company.
Dr Cunningham and Mr Weber are Members of the Australasian Institute of Mining and Metallurgy and have sufficient relevant experience to the style of mineralisation and type of deposit under consideration and to the activities undertaken to qualify
as a Competent Person as defined in the 2012 Edition of the Joint Ore Reserves Committee (JORC) Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves.
The Competent Persons consent to the inclusion in this report of the matters based on the information compiled by them, in the form and context in which it appears.
Competent Person Statement for JORC 2012 Mineral Resources – Cattle Grid South
The information in this statement that relates to the Mineral Resource Estimates is based on work done by Dr Michael Cunningham of SRK Consulting (Australasia)Pty Ltd (SRK).
Dr Cunningham is a Member of The Australasian Institute of Mining and Metallurgy and has sufficient experience that is releva
nt to the style of mineralisation and type ofdeposit under consideration, and to the activity he is undertaking, to qualify as a
Competent Person in terms of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code, 2012).
Competent Person Statement
APPENDIX A: STATEMENTS
Coda Minerals - Sustaining Tomorrow
17
Aggregated Mineral Resources at Elizabeth Creek
APPENDIX B: MINERAL RESOURCES
OPEN PIT Proposed Tonnage Cut-off Copper Cobalt Silver Zinc Copper Equivalent
Resource Category Type Mining Mt Grade Grade Contained Grade Contained Grade Contained Grade Contained Grade Contained
Method (% Cu) Metal (t) (ppm Co) Metal (t) (g/t Ag) Metal (Moz) (ppm Zn) Metal (t) (% CuEq) Metal (t)
MG14 Indicated Zambian Open Pit 1.8 0.5% CuEq 1.2% 22,700 330 600 14 0.8 1.7% 30,600
Cattle Grid South Inferred Breccia Open Pit 5.8 0.2% Cu 0.6% 36,000 120 700 3.5 0.7 684 4000 36,000
Windabout Indicated Zambian Open Pit 17.7 0.5% CuEq 0.8% 136,100 490 8700 8 4.6 1.4% 249,100
Sub Totals Indicated Zambian Open Pit 19.5 0.5 CuEq 0.8% 158,800 480 9300 8.5 5.4 1.4% 316,000
(Open Pit) Inferred Breccia Open Pit 5.8 0.2% Cu 0.6% 36,000 120 700 3.5 1 684 4,000
UNDERGROUND Proposed Tonnage Cut-off Copper Cobalt Silver Zinc Copper Equivalent
Resource Category Type Mining Mt Grade Grade Contained Grade Contained Grade Contained Grade Contained Grade Contained
Method (% Cu) Metal (t) (ppm Co) Metal (t) (g/t Ag) Metal (Moz) (ppm Zn) Metal (t) (% CuEq) Metal (t)
Indicated Zambian Underground 37.5 1% CuEq 1.3% 485,000 590 22,000 17 20.6 1800 66000 1.9% 715,000
Emmie Bluff Inferred Zambian Underground 2.7 1% CuEq 0.9% 26,000 280 1,000 12 1.1 1700 5000 1.3% 36,000
Sub Total
(Underground)
Combined Zambian Underground 40.2 1% CuEq 1.3% 511,000 570 23,000 16.8 21.7 1700 70000 1.9% 751,000
Project Wide Total 65.5 Mt 705,800t Contained Cu 33,000t contained Co 28 Moz Contained Ag 75,000t Contained Zn 1,067,000t contain CuEq
[1] No Copper Equivalent was calculated for Cattle Grid South. Contained CuEq tonnes quoted in this column for Cattle Grid South consist of contained copper only.
[2] Total figures have been aggregated purely for convenience and to contextualise the specific contribution of individual Mineral Resource Estimates to the overall project scale. Grades reported are tonnage-weighted averages of the individual Mineral
Resource Estimates. Coda notes that the total figure includes resources reported at varying cut-off grades, with varying estimation techniques, metallurgical properties and proposed mining methods. Individual Mineral Resource Estimates should be considered
individually. A total copper equivalent figure has not been disclosed as Coda does not believe it is currently appropriate to calculate a copper equivalent for the Cattle Grid South Mineral Resource Estimate. Please see below sections Statement Regarding Metal
Equivalent Calculations and Competent Persons Statement for full details on the calculation of copper equivalents and links to original releases/CP statements. Figures have been rounded for simplicity.
[3] No Zinc estimate was provided for the MG14 and Windabout deposits. This figure reflects the contained tonnage solely from Emmie Bluff and Cattle Grid South.
Coda Minerals - Sustaining Tomorrow
18
Statement Regarding Metal Equivalent Calculations
APPENDIX C: METAL EQUIVALENT CALCULATIONS
Metal Equivalent grades are quoted for one or more of the Emmie Bluff, Windabout and MG14 Mineral Resources, or for exploration results considered by the company to be related directly to one of these Mineral
Resources, in this announcement.
For the Emmie Bluff Mineral Resource:
The Emmie Bluff Mineral Resource is reported as 40.2Mt @ 1.27% copper, 569ppm cobalt, 17g/t silver and 0.17% zinc (1.87% Copper Equivalent (CuEq)) reported at a cut-off grade of 1% CuEq. The calculation of this
metal equivalent is based on the following assumptions.
Price assumptions used when calculating copper equivalent grades were based primarily on Consensus Economics forecasts of metals, except for Cobalt, which was sourced via communication with subject matter
experts. Metallurgical assumptions used when calculating copper equivalent grades were based on a simple bulk float utilising rougher and minimal cleaner/scavenger circuits. The produced a reasonably consistent
mean recovery across most metals of between approximately 83 and 94 percent. For simplicity, and to in part account for losses associated with less intensive cleaner floats and losses to the hydromet plant, these
figures were rounded down to the nearest 5%.
Application of these assumptions resulted in the following calculation of CuEq:
𝐶𝑢𝐸𝑞% = 𝐶𝑢%+ 0.00068×𝐶𝑜 𝑝𝑝𝑚 + 0.337×𝑍𝑛 % + 90.3×
𝐴𝑔 𝑝𝑝𝑚
10000
For the Windabout and MG14 Mineral Resource:
The Windabout and MG14 Mineral Resource are reported at a cut-off grade of 0.5% CuEq as:
• Windabout: 17.67Mt @ 0.77% Cu, 492 ppm Co and 8 g/t Ag (1.41% CuEq)
• MG14: 1.83Mt @ 1.24% Cu, 334 ppm Co and 14 g/t Ag (1.84% CuEq)
Metal Coefficient Forecast Price Price Unit
Copper 0.8 $7,000 USD/Tonne
Cobalt 0.85 $55,000 USD/Tonne
Zinc 0.9 $2,100 USD/Tonne
Silver 0.85 $18.50 USD/Oz
Coda Minerals - Sustaining Tomorrow
19
Statement Regarding Metal Equivalent Calculations (continued)
APPENDIX C: METAL EQUIVALENT CALCULATIONS
The calculation of this metal equivalent is based on the following assumptions:
Price assumptions used when calculating copper equivalent grades were based on recent historical metal prices at the time of calculation (2018). Metallurgical assumptions are based on extensive metallurgical
testwork undertaken on the two deposits to 2018 across various potential flowsheets involving both floatation and leaching. Ag analyses in the estimation and metallurgical testwork were considered insufficient at the
time to include in the metal equivalent calculation.
Application of these assumptions resulted in the following calculation of CuEq:
𝐶𝑢𝐸𝑞% = 𝐶𝑢%+ 0.0012×𝐶𝑜 𝑝𝑝𝑚
It is the opinion of the company that both sets of prices used in the calculations are reasonable to conservative long-term forecasts for real dollar metal prices during the years most relevant to the deposits (approx.
2026-2030).
It is the opinion of the company that all of the elements included in the metal equivalent calculations have a reasonable potential to be recovered and sold.
For full details of the Emmie Bluff Metal Equivalent calculation, please see “Scoping Study Update Delivers Materially Improved Economics” released to the market on 30th January 2024 and available to view at
https://www.codaminerals.com/wp-content/uploads/2024/01/20240130_Coda_ASX-ANN_Scoping-Study-Update-Delivers-Materially-Improved-Economics_RELEASE.pdf.
For full details of the MG14/Windabout Metal Equivalent Calculation, please see “Confirmation of Exploration Target & Mineral Resource and Ore Reserve Statement”, released to the ASX on 23rd October 2020 and
available at https://www.coda
Share your feedback
Discover