Mining Study Marks Key Breakthrough at Elizabeth Creek
Released
Released
Announcement PDF
ASX RELEASE
22 November 2022
ASX Code: COD
Mining Study Marks Key Breakthrough at Elizabeth Creek
Study confirms a technically viable pathway to achieve steady-state 2.5Mtpa production
Highlights
• Positive Scoping-level mining study completed for the cornerstone Emmie Bluff copper-cobalt deposit, with a strong
“go-forward” initial mine plan completed and no technical barriers to mining identified.
• Mining method utilises conventional drill-and-blast techniques and an industry-standard mining fleet for a planned
steady-state production rate of 2.5Mtpa. Flat Long-hole Open Stoping with Pillars selected as the optimal mining
method.
• Proposed open pit extraction of the satellite MG14 and Windabout deposits will allow the operation to rapidly achieve
nameplate metal production during the development and ramp-up of the Emmie Bluff Underground Mine.
• Underground Mining Study provides an excellent base case, with improvement and optimisation opportunities to be
progressed into next phases of studies.
Scoping Study Update
• Final scoping-level design and cost estimates received for the Elizabeth Creek processing plant from Coda’s
metallurgical consultants, Strategic Metallurgy, with the data currently being reviewed.
• With the completion of the mine plan and capital and operating costs, Coda is now integrating all of this information
and compiling and reviewing the financial models which will underpin the Scoping Study.
• Scoping Study on track for delivery in Q1 2023, once trade-off studies are completed.
• Coda’s cash balance is approximately $8 million, leaving the Company well-funded to complete this pivotal study work
and continue to advance critical path items for the development of the Elizabeth Creek Copper Project.
Coda Minerals Ltd (“Coda” or “the Company”) is pleased to advise that it has achieved a key breakthrough in its plans to
develop a long-term copper mining operation at the 100%-owned Elizabeth Creek Project in South Australia’s Olympic
Copper Province after receiving very positive results from recently completed underground and open pit mining studies.
The mining studies encompassed the
cornerstone Emmie Bluff underground deposit
and the satellite MG14 and Windabout open pit
copper-cobalt-silver deposits.
The Emmie Bluff Mining Study, which was
undertaken by independent consultants Mining
Plus Pty Ltd, has confirmed the technical
viability of mining the large Emmie Bluff deposit
using conventional mining methods at the
desired production rate, establishing a strong
“go-forward” case that will inform the ongoing
Scoping Study.
6 Altona Street
West Perth
Western Australia, 6005
Figure 1. Isometric view of proposed Emmie Bluff stope model.
E: info@codaminerals.com
The proposed mining schedule would see the Emmie Bluff deposit mined over a 17-year mine life at a steady-state
production rate of 2.5 million tonnes per annum (Mtpa). Mining will be undertaken using conventional underground drilland-blast methods and utilising a standard underground mining fleet.
Of the four underground mining methods evaluated, the optimal method selected was Long-hole Open Stoping with
Pillars. Total mined ore over the life of mine is anticipated to be in excess of 26 million tonnes at an average grade of
1.86% CuEq 1 (see Table 1). Importantly, no technical barriers were identified to achieving the higher production rates
required to optimise returns from the Project.
Coda has also engaged Crystal Sun Consulting to undertake mining engineering studies into the shallower open-pit
deposits MG14 and Windabout. Material from these deposits is expected to total 1.3Mt at 1.42% Cu and 371 ppm Co
(MG14) and 6Mt at 1.03% Cu and 667 ppm Co (Windabout). This mineralisation will supplement the Emmie Bluff material,
providing mill feed during ramp-up and development of the underground mine to allow the operation to rapidly achieve
nameplate capacity for the proposed Emmie Bluff processing plant, which is currently expected to be 2.5Mtpa.
Commenting on the results of the study, Coda CEO Chris Stevens said:
“This is a critical breakthrough and very exciting achievement by our development team at Elizabeth Creek. At the heart
of this is the Emmie Bluff Underground Mining Study, which demonstrates that this deposit can be productively mined
using conventional mining methods, reducing the project’s risk profile. The flat-lying geometry and narrow nature of the
lodes at Emmie Bluff make it a more challenging proposition from a mechanised hard rock mining point of view than some
Australian mineral deposits, which tend to have a greater vertical dimension. However, this style of mineralisation is
commonly mined in Africa and Europe, and we are pleased to have now demonstrated a suitable mining method with
strong throughput at reasonable mining costs.
“As a scoping level study, there are clearly a number of areas that we will address as part of the next level of studies
including the potential to optimise and bring forward early production rates, consideration of alternative mining methods
including mechanical cutting, and the potential for more efficient fleets including electric mining vehicles. However, this
study represents an excellent base case and we are very pleased with the results.
“The completion of this Study, and in particular the key physicals and mine scheduling data that have been generated,
represent some of the final key inputs towards the completion of the Elizabeth Creek Scoping Study. We are now moving
rapidly towards finalising the Scoping Study, with integration of the mine plan, capital and operating cost estimates and
completion of the financial model. We are on track to complete this work and deliver the Study by mid Q1 2023.”
1
The Company notes that this estimate constitutes a Production Target in line with ASX Guidance Note 31, and is therefore a forward-looking
statement. The Company has undertaken extensive due diligence before reporting this information, the details of which make up the bulk of this
announcement. The estimated Mineral Resources underpinning the Production Target have been prepared by a Competent Person in accordance
with the requirements the JORC Code 2012. For full details, including JORC Table 1, please “Standout 43Mt Maiden Cu-Co Resource at Emmie Bluff”,
released to the ASX on 20th December 2021 and available at https://www.codaminerals.com/wp-content/uploads/2021/12/20211220_Coda_ASXANN_Standout-43Mt-Maiden-Cu-Co-Resource-at-Emmie-Bluff_RELEASE.pdf, and “Confirmation of Exploration Target & Mineral Resource and Ore
Reserve Statement”, released to the ASX on 23rd October 2020 and available at https://www.codaminerals.com/wpcontent/uploads/2020/10/20201026_Coda_ASX-ANN_Confirmation-Statements-JORC.pdf.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
Figure 2. The anticipated metal production schedule for all three deposits based on mining and metallurgy studies completed to date. “All Deposit CuEq” is calculated as value of produced cobalt, silver and zinc divided
by assumed copper price (8,800 USD) Assumed metal recoveries and prices used are as set out in JORC table 1, below.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
Summary of Scoping Level Mining Study – Emmie Bluff Deposit
Table 1 Summary of Emmie Bluff’s calculated mining physicals
Mining Physicals
Total Mined Ore
Mined Ore Grade
Mined Waste
Waste/Ore Ratio
Capital development (Lateral)
Operating development (Lateral)
Development ore
Stope/development ore
Unit
t
CuEq%
t
t/t
m
m
t
t/t
Value
26,229,818
1.86
956,516
0.036
25,842
96,459
7,266,061
2.61
Coda engaged mining consultants Mining Plus to undertake a comprehensive underground mining study of the Emmie
Bluff deposit. The scope of works included the collating and reviewing of relevant input data (including the geological
model provided by Coda and previous studies, geotechnical review, mining method selection, mine design and
scheduling, and optimisation in line with high-level financial modelling. The physicals of the study are summarised in
Table 1, and production over time for Emmie Bluff is outlined in both Figure 2 and Figure 4. Additional detail is provided
below.
Input Parameters
Non-mining input parameters (e.g. processing costs, metal recoveries, commodity prices, FOREX etc.) were developed
by Coda and provided to Mining Plus based on work carried out by Coda Minerals as part of the broader ongoing
scoping study into the Elizabeth Creek copper-cobalt project.
Mining Method Selection
Mining Plus considered four mining methods based on the key characteristics of the orebody: mineralisation at Emmie
Bluff lies approximately 400m below the surface and is composed of a pair of flat dipping, laterally extensive lodes with
substantial plan view area, but low thickness (between 2 and 15m). The methods considered were:
•
•
•
•
Longhole Open Stoping with pillars
Longhole Open Stoping with paste fill
Drift and Fill
Drift and Fill with wall stripping
Ultimately, Longhole Open Stoping with pillars was chosen as the preferred mining method.
Longhole open stoping is conducted by developing drill drives, and slots with longhole stope rings fired into the
open/developed slot drive. Pillars are left between the stopes for stability within the active mining areas, thus reducing
overall ore body recovery. Geotechnical guidelines and ore boundaries determine pillar dimensions. This method allows
larger capacity drills and loaders based on the chosen development size.
The benefits of longhole open stoping with pillars include multiple faces being available to work simultaneously, no
backfilling required and low ore body dilution where the mineralisation thickness is the same or greater than the drive
size height.
The method was chosen due to its flexibility and high-productivity mechanisation, enabling multiple headings and work
areas to be established, increasing the production rate.
The Drift and Fill methods were discarded due to their lower productivity and higher cost. The large plan-view area of the
orebody, widths accommodation, larger mining equipment and the grade distribution enable the productive and lowcost Longhole Open Stope method to create a flexible mining process with good selectivity.
Longhole Open Stoping with paste fill was considered; however tight paste filling flatter stopes have multiple technical
challenges.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
Paste filling is productive when stopes dip at 5° or more and where the metal grades support greater extraction despite
the more significant investment. Mining recovery is also inversely proportional to stope height, with pillar volume
increasing in line with stope heights. However >10m high stopes are only 2% of the inventory, and methods to improve
extraction is high-grade areas will be investigated during later studies., but was not considered a sufficiently economically
robust option for the base case. Similarly, consideration will be given to pillar scavenging, a variation of the method where
the pillar size can be reduced by adding backfill, depending on the geotechnical stability.
Geotechnical characteristics
Mining Plus engaged Cartledge Mining and Geotechnics, a specialist geotechnical firm, to undertake a concept study to
determine the maximum excavated spans and pillar requirements. The majority of the mineralisation at Emmie Bluff is
located at the upper contact between the Tapley Hill Formation black shale and the Whyalla Sandstone, which was
determined to be a very stable and strong (hanging wall) beam, with good geotechnical characteristics as a roof. The
black shale of the Tapley Hill Formation is a geotechnically inferior, fissile body with poorer rock mass ratings and
overall strength, requiring relatively large pillars as a consequence. Tapley Hill Formation shale at Emmie Bluff is
assumed to have a bulk density of 2.75.
Stoping and pillar dimensions were derived for 2 scenarios, both assuming no paste fill is used:
• ≤ 5m high, supported backs:
o 2:1 Stope height to pillar size ratio, i.e. 10m (W) x 10m (L) transverse pillars required or 10m (W) x
10m (L) longitudinal pillars required for a 5m high stope. (See Figure 3)
•
> 5m high, unsupported backs:
o 2.5: 1 Stope height to pillar size ratio
Ground support for stoping areas and capital development will require 2.4 m resin bolts in both the backs and walls
with welded mesh. Cable bolts will be installed at intersections and where needed but will not be used to support the
backs of stopes. The stopes were recommended to strike parallel to the principal stress, so the stopes were designed
accordingly.
Table 2 Metallurgical and assumed metal price characteristics for Emmie Bluff mining study
Cu
Co
Ag
Zn
8,800/t
60,500/t
17/oz
2,280/t
12,941/t
88,971/t
24/oz
3,353/t
Government Royalty
3.50%
3.50%
3.50%
3.50%
Units- Metal to grade
1
1
0.032
1
Units factor
1
1
31.103
1
Final product payability
100%
100%
100%
100%
Average LOM concentrate grade
18%
1.10%
312g/t
1.90%
Metal price USD
Exchange rate AUD: USD
Metal price AUD
0.68
Metallurgical recovery
74%
90%
87%
91%
NSR*/grade unit
9,274
77,177
0.656
2,944
71.70%
86.70%
84.10%
87.80%
1
8.322
0.0071
0.317
Factor - Gross value to mined value
Equivalence factor
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
Cut-Off Grade Selection and Stope
Optimisation
A cut-off grade calculation was made based on known
metallurgical characteristics, assumed average lifetime
commodity prices (See Table 2) and mining operating
costs, which were calculated based on the selected mining
method using a unit rate calculator and Mining Plus’s
internal database; the total stoping cost was AUD54 per
tonne. All mining costs assume contractor mining.
This value was factored with 29% to development and 71%
to production for the resulting value of AUD56.14 2 per
mined tonne, resulting in a nominal cut-off grade of 1.1%
CuEq prior to stope optimisation.
Stope shapes were created using Datamine MSO; the
analysis was performed for various CuEq grade increments
between 0.8% and 1.4%. A cut-off grade of 1.2% was
chosen for the design and schedule to account for
additional dilution at the scheduling phase to account for
the different lodes and roof heights to the lode boundary.
Table 3 shows the difference in tonnes depending on which
cut-off grade was used.
Table 4 Assumed OPEX characteristics for cut-off grade calculation
Operating Cost
Figure 3 Stope parameters and pillar positioning
Unit
Value
Mining
AUD/t mined
56.14
Processing - Final Products
AUD/t mined
39.5
Site General & Administration (G&A)
AUD/t mined
5
Total Costs
AUD/mined t
100.64
Cut-off
CuEq Grade
1.08%
1.0
35.9
1.74
623.1
AUD/t
66
1.2
27.6
1.93
533.4
CuEq Grade
1.10%
1.4
21.9
2.10
459.0
NSR feed grade
Diluted Cut-off grade (rounded)
Table 3 Tonnes and Grades at various cut-off grades following
stope optimisation.
Cut-Off
Grade (%)
Stope
tonnes (M)
CuEq
CuEq Metal
Contained (kT)
Mine Design and Scheduling
The ore body will be accessed via a decline from the surface in a low-grade/waste area located at the centre of the deposit
(see Figure 5). The decline has a gradient of -1:7 and is sized to permit the operation of 51 tonne underground haul trucks
with allowances for ventilation ducting and mine services.
A series of rises developed next to the decline will initially be used for return air. Once the long-term return air rises are
developed these rises will be converted into an additional fresh air intake. Three long-term return air rises located at the
outer limits of the ore body and one additional fresh air rise, 150 m east of the decline, will be developed to the surface
(see Figure 5). The designed mine ventilation strategy was verified to ensure that ventilation flows throughout the mine
were suitable for the planned equipment and scheduled activities and that the location and dimension of all airways suit
the overall system air flows and pressures.
The stope design was based on a 100m long x 30m wide area. The MSO shapes were created at 10m x 30m and then
manually connected at similar heights and within the same lode, ranging between 30m and 130m in length (Figure 5-4),
2 Calculated as $61.40 per tonne for development and $53.73 for production, excluding capital costs.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
with the majority kept to 100m length or below as per the study guidelines. This technique meant that smaller stopes
could be included, and groups of large stopes could also be mined together. Each of the stopes were designed with a slot
drive. There were 6,766 MSO shapes, and when combined and isolated shapes were removed, 959 mineable stopes were
created (See Figure 6).
Capital development (declines, stope accesses and ventilation infrastructure) takes place in the first four years, prior to
the commencement of stoping. As much as practical, development has been designed to take place in mineralised
material to minimise mined waste (<1Mt of waste is expected to be mined over the life of mine, including the decline).
Sequencing of stopes following capital development was unconstrained geotechnically 3, thus priority was given to the
highest grade areas of the deposit to maximise early revenue. Scenarios were considered in 0.5 Mtpa intervals from 2.0
to 3.5 Mtpa, with 2.5 Mtpa ultimately selected.
The 2.5 Mtpa option was chosen as the preferred option because production rates can be maintained for 9 years without
additional capital development. This volume saw the maximum number of trucks (12) utilised most efficiently before a
single decline became insufficient due to traffic, rendering it the most capital efficient.
3000000
2.5
2500000
2
2000000
1.5
1500000
1
1000000
CuEq %
Tonnes Mined
Mined Production, Emmie Bluff
0.5
500000
0
0
High Grade Ore
Low Grade Ore
High Grade Ore, Grade, CuEq %
Low Grade Ore, Grade, CuEq %
Figure 4 Emmie Bluff anticipated mine schedule. Ramp up following decline construction in years 1 and 2 will be compensated for with mineralised from
the open pit deposits at Windabout and MG14,
3
Except in areas where both upper and lower Tapley stopes are economical to mine. In these circumstances, the upper lode is scheduled first to avoid
undercutting.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
Figure 5 Plan view (upper) and view looking north (Lower) of decline and ventilation infrastructure.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
Figure 6 MSO shapes (left) combined into Minable Shapes (right)
Equipment Selection
It was determined early in the study that productive mining of the Emmie Bluff ore body demanded equipment of a
certain scale. To ensure high productivity, the goal was to stay within a drive size that could accommodate 17t loaders
and 51 tonne trucks, while not materially exceeding these heights to minimise dilution in the flat-lying ore body. It is
important to note that the following fleet is considered conceptual and represented the basis on which assumptions
about mining cost, drive heights and productivity were made however alternative equipment of comparable or better
specifications will be considered at a later date as part of further feasibility studies, when undertaken.
Of particular note is the choice to design around a diesel-based fleet: this was done for simplicity and to develop a
baseline for potential productivity using modern equipment and techniques. However the company intends to carefully
consider the options for a fully or partially electrified fleet as part of later studies, to minimise carbon emissions, reduce
ventilation requirements to manage the diesel particulate concentration and heat, and due to the potential for
productivity improvements in certain applications.
Drill rig (Jumbo) - Sandvik DD4421
The Sandvik DD4421 was chosen for the development drill rig; the closed cab configuration can fit in the smaller ore drives (and large
ones) if the ventilation ducting is located on the sidewall, with enough room for pedestrian access.
Long hole drill rig - Sandvik DL431
The Sandvik DL431 or equivalent was chosen as it can efficiently drill near parallel long holes to the floor and backs.
Loader - Sandvik LH517i
The Sandvik LH517i or equivalent was selected; this loader can fit into the smallest stope sizes, where ventilation ducting isn’t
required. It is also designed to work with the selected TH551i truck (3-passes system).
Truck – Sandvik TH551i
The TH551i diesel truck or equivalent was chosen as it is the largest truck that the LH517i can quickly load. The minimum drive size
required with ventilation ducting is 5.5 m high; accessways were designed through the mine to be used as trucking routes.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
Summary of Open Pit Mining Study – Windabout and MG14 Deposits
Coda engaged mining consultants Crystal Sun Consulting to undertake a comprehensive open-pit mining engineering and
pit optimisation study of the MG14 and Windabout deposits. The scope of works included the collation and review of
relevant input data (including the geological models provided by Coda) and previous studies, mine design and scheduling,
and optimisation in line with high-level financial modelling.
Input Parameters
Non-mining input parameters (e.g. processing costs, metal recoveries, commodity prices, FOREX etc.) were developed
by Coda and provided to Crystal Sun on the basis of work carried out by Coda Minerals as part of the broader ongoing
scoping study into the Elizabeth Creek copper-cobalt project. Crystal Sun also made use of data provided by Mining Plus
to efficiently integrate the two production schedules.
Cut-Off Grade Selection
Marginal cut-off grade at MG14 and Windabout was based on the cost of transport from the pits (which are
approximately 40km away via an assumed haul road route from the proposed process plant at Emmie Bluff), the cost of
processing and metallurgical recoveries known from testwork. This was determined to be 0.6% CuEq.
Mining costs were calculated based on a cost model developed in 2022 including inputs from a reputable South Australian
based mining contractor. Costs included Mine Technical Services, Load and Haul, Drill and Blast, Grade Control,
Dewatering, Messing & Accommodation, and assumed contract mining. Tapley Hill Formation shale at MG14 and
Windabout was assumed to have a dry bulk density of 2.2 dmt/bcm.
Table 5 Estimated mining costs,
MG14 and Windabout open pits.
Depth
(m)
Waste
AUD/dmt
Ore
AUD/dmt
10
1.93
2.39
20
2.26
2.79
40
2.64
3.27
60
2.98
3.68
80
3.14
3.82
100
3.28
4.12
Pit Shell Optimisation and Design
The pit optimisation process was run using Hexagon Mining's Mine Economic Planner
software, assuming pit wall slopes of 45-55 degrees. This resulted in a single optimised
pit at MG14 and four pits at Windabout, which can be seen below as Figure 7 and Figure
8 respectively.
The bases of the designed pit floors were set to the lower surfaces of the optimised pits,
batter slopes of pit walls were set at 65 degrees with a 5 metre berms every 20 metres,
and ramps of 25-30m width with maximum gradients of 10% have been included. These
designed pits resulted in the mineral inventory in Table 6.
Table 6 Mineral Inventory assumed for the Mining Study at MG14 and Windabout. A progression from Indicated Resources to Proven and Probable
Reserves for the open pits was not part of the scope of work for this study, so a Mineral Inventory has been presented, not a Mineral Reserve.
Mineral Inventory
MG14
Windabout
Total
6 Altona Street
West Perth
Western Australia, 6005
Ore (Mdmt)
1.257
5.959
7.216
Cu (%)
1.42
1.03
1.10
Co (ppm)
371
667
616
E: info@codaminerals.com
Ag (g/t)
15.6
11.2
12.0
CuEq (%)
1.87
1.72
1.74
Overburden
(Mdmt)
14.1
128.2
142.4
Strip ratio
11.2
21.5
19.7
Figure 7 MG14 Optimised Pit Base Case: 500m grid
Figure 8 Windabout Optimised Pit Base Case: 500m grid
Proposed Mining Methodology
Mining at MG14 and Windabout will employ a conventional pit-strip and staged open pit mining system that involves
several phases including the following:
Site Preparation works and land clearing
Land clearing will commence ahead of mining and will include clearing of shrubs, and removal of humus just ahead of
overburden removal. Dozers, excavators and trucks and/or scrapers will undertake this work. This material will be
stockpiled at designated areas for use in future rehabilitation works.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
Prior to any earthworks being carried out, excavators and dozers will be used to construct drainage and diversion
channels to direct runoff into settling and sedimentation ponds
Overburden Removal and Storage
The mining of MG14 and Windabout deposits will involve conventional open pits, selective mining methods, using
mining, drilling and blasting and ore haulage contractors. The initial mine development of the open pits will include box
cuts & pre-stripping in both deposits.
Bulk overburden stripping will be carried out on 10 metre benches mined on 4-5 metre benches using 400 tonne
excavators loading 194 tonne capacity dump trucks. Drilling and blasting is anticipated to be required from 15-20
metres, above which mining is anticipated to be carried out on a free dig basis. Drilling and blasting will be performed
on 10 metre high benches in overburden, and 5 metre benches near the ore zones.
Ore and Waste Mining, Ore Stockpiling and Ore Rehandling
Ore mining with be carried out on 5 metre benches mined in to 2.5 metre flitches using a 130-200 tonne excavator
loading 60-90 tonne capacity dump trucks. The mining fleet will include 6 hydraulic drill rigs and ancillary fleet for dump
management and road maintenance.
Drilling and blasting will be performed on 10 metre benches in overburden, and 5 metre benches near the ore zones.
Blasthole cuttings in ore zones will be sampled and assayed at an onsite assay laboratory. A grade control system will
be used delineate ore and waste zones.
Stockpiling will be done at the main stockpile areas near MG14 and Windabout prior to transport to the Emmie Bluff
processing plant via a haul road, expected to be designed in parallel with power infrastructure heading to the
underground mine. The assumed length of this road is 40km for the purposes of the mining study.
In-Pit Backfilling and Progressive Rehabilitation
Overburden will be pre-stripped at both MG14 and Windabout pits and placed adjacent to the starter open pits at each
deposit until such time as progressive backfilling can commence. Progressive backfilling will continue at each pit for the
duration of the project. Maximum height of overburden emplacements will be 20 metres above the natural surface.
Figure 9 Anticipated final status of overburden storage at the MG14 pit showing overburden emplacement and progressive backfilling of eastern end of
pit.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
Scheduling
Mining scheduling is designed to integrate with the Emmie Bluff schedule to ensure availability of mill feed during the
ramp up at the Emmie Bluff deposit.
3000000
2.5
2500000
2
2000000
1.5
1500000
1
1000000
CuEq %
Tonnes Mined
Mined Production, Elizabeth Creek
0.5
500000
0
Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year Year
1
2
3
4
5
6
7
8
9
10 11 12 13 14 15 16 17
MG14 Ore
Windabout Ore
EB Low Grade Ore
EB High Grade Ore
EB High Grade Ore, Grade, CuEq %
EB Low Grade Ore, Grade, CuEq %
0
Weighted Average Grade, MG14 and Windabout, CuEq%
Figure 10 Overall anticipated production schedule, Elizabeth Creek project.
Equipment Selection
The primary fleet will consist of two 400 tonne hydraulic excavators loading units and 194 tonne capacity dump trucks
mining overburden. A smaller fleet has been chosen for mining ore, allowing for more selective extraction: this will consist
of a 130 - 200 tonne excavator unit and 90 tonne capacity trucks.
Trucking requirements, cycle times and average truck speeds were determined using Caterpillar Fleet Production Cost
software. The trucking requirements fluctuate throughout the operating periods due to fluctuations in haulage distances.
Tracked dozers (337 kW) will be utilised for pit development and floor maintenance, and stockpile and dump
maintenance, and rehabilitation works.
Motor graders (216 kW) and Water Trucks will be utilised to maintain pit haul roads, the port haulage road and all access
roads on the project site.
Topsoil and overburden material removal will be carried out by small hydraulic excavators, loading 30 tonne capacity
articulated mining trucks and/or scrapers for transport to overburden dumps, stockpiles, or mined out areas.
The Company will investigate opportunities for alternative mining equipment, including electric fleet as part of ongoing
feasibility work after delivery of the Scoping Study.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
Figure 11 Approximate assumed layout of Elizabeth Creek Project
Planned and Ongoing Work
With the mining studies now completed, the Company has now received the majority of its outstanding thirdparty research. The company is currently focussing on integration of the mine plan information into the overall
study framework as well as integrated value chain optimisation and finalisation of financial models to underpin the
Scoping Study.
As a scoping level study, the current work leaves open multiple avenues and opportunities for value improvement,
optimisation and trade off studies. These include further study and optimisation of the Emmie Bluff mine plan to bring
forwar