December 2023 Quarterly Activities and Cashflow Reports
Released
Released
Announcement PDF
ASX RELEASE
31 January 2024
ASX Code: COD
QUARTERLY
ACTIVITIES REPORT
FOR THE QUARTER ENDED 31 DECEMBER 2023
HIGHLIGHTS
CONTENTS
1.0
Overview
2.0
Projects & Assets
2.1
Tenement
Schedule
2.2
Elizabeth Creek
Copper Project
Update
2.3
Future Work
Programme
3
Corporate
3.1
Finance &
Use of Funds
4
Events
Subsequent to
Quarter End
Elizabeth Creek – Copper-Cobalt Project (South Australia)
- Focus for the quarter was the completion of the Updated Elizabeth Creek CopperCobalt Project Scoping Study (released on 30th January 2024).
- The Study Update demonstrates an approximate project NPV8 of $735m, a 29%
increase relative to the March 2023 study.
- Work to facilitate this release during the quarter included finalisation of mechanical
cutting mining studies and optimisation of processing options.
• Elizabeth Creek – IOCG (South Australia)
- Detailed new geophysical interpretation of Emmie IOCG completed, refining Coda’s
exploration model and suggesting scope to extend the deposit along strike to the
north and south.
• Other – Kinloch Project
- Successful joint application with Boss Energy, for the “Kinloch” project, covering the
Cambrian-Ordovician Delamerian Orogen basement rocks and the overlying Cenozoic
Murray Basin sediments in eastern South Australia.
- Coda will hold the base metals rights for the tenure, with Boss Energy to hold uranium
rights.
• Corporate
- $1.9 million cash on hand as at 31 December 2023.
- Cost savings implemented during the quarter have materially reduced cash burn rate.
- The Company is continuing to actively investigate and advance funding options and
has made excellent progress to date, with significant inbound interest received from
potential funding and strategic partners.
• Upcoming Milestones
- Ongoing optimisation of Elizabeth Creek Study including paste fill and optimised
flotation options.
- Results of recent IOCG geophysical review and higher precision targeting
- Review of uranium prospectivity at Cameron River
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN: 49 625 763 957
1. Overview
Coda Minerals Chair, Keith Jones, said: “Our focus during the quarter was on the completion of workstreams required for
the finalisation and release of the Elizabeth Creek Copper Project Scoping Study Update.
“This work included studies on the application of mechanical cutting to the mining of Emmie Bluff and optimisation of
reagents and processes for the processing of the copper-cobalt mineralisation from all deposits at Elizabeth Creek.
“The updated study1 demonstrates the upside value at Elizabeth Creek. The forecast NPV8 is now projected to be $735
million with a pre-production CAPEX of just $306 million. This represents an increase to NPV of $165 million or 29%
compared to the previous study.
“The Coda team has demonstrated the ability to significantly improve project economics and reduce risk through
optimisation. The focus during the March quarter will be on investigation of paste fill to optimise extraction at Emmie
Bluff as well as new flotation techniques to drive flotation recoveries across the flowsheet. These opportunities offer
significant upside opportunities and are expected to further enhance project economics.
“Our exploration pipeline remains extremely strong as we build on work completed in 2023 and finalise drill targets
seeking to extend Emmie Bluff2. We continue to build our understanding of Emmie IOCG having recently completed a new
targeting study with results expected during the March quarter.
“The grant of tenure during the December Quarter together with Boss Energy at Kinloch demonstrates our commitment
to regional copper exploration and building a long-life copper pipeline in South Australia.
“With the completion of a major study update, progress with our exploration at Elizabeth Creek and enhancing our
regional exploration pipeline, the December quarter was extremely busy and productive. We look forward to building on
this work into the March 2024 quarter.”
1
Please see “Scoping Study Update Delivers Materially Improved Economics”, available at https://www.codaminerals.com/wpcontent/uploads/2024/01/20240130_Coda_ASX-ANN_Scoping-Study-Update-Delivers-Materially-Improved-Economics_RELEASE.pdf
2 Please see “New Copper-Cobalt Drill Targets Defined at Emmie Bluff”, available at https://www.codaminerals.com/wpcontent/uploads/2023/07/20230704_COD_ASX-ANN_New-Copper-Cobalt-Drill-Targets-Defined-at-Emmie-Bluff_VRelease.pdf
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
2. Projects & Assets
2.1 Tenement Schedule
In accordance with ASX Listing Rule 5.3.3, Coda provides the following information about its tenements for the quarter ended 31 December 2023.
Table 1 Coda tenement schedule
Grant Date
Expiry Date
Area
km2
Ownership
SA
29 October 2017
28 October 2028
47
100%
Elizabeth Creek
SA
25 March 2020
24 March 2025
363
100%
EL 6265
EL 6945
EL 6917
EPM 27042
Elizabeth Creek
Elizabeth Creek3
Booleroo
Cameron River
SA
SA
SA
Queensland
7 October 2018
17 October 2023
25 July 2023
10 October 2019
6 October 2029
16 October 2029
24 July 2029
9 October 2024
291
73
202
22.4
100%
100%
100%
51%4
EPM 27053
Cameron River
Queensland
14 February 2020
13 February 2025
12.8
51%5
EL 7342
EL 7584
EL 9238
Club Terrace
Club Terrace
Club Terrace
Victoria
Victoria
NSW
19 August 2020
18 January 2021
29 August 2022
29 August 2022
3 August 2021
28 August 2027
28 August 2027
3 August 2027
375
108.5
260
100%
100%
100%
EL 7637
Balmoral
Victoria
17 June 2021
29 August 2022
28 August 2027
835
100%
EL 2690
Rigo
26 January 2022
26 January 2024
1164
100%
EL 6962
EL 6963
EL 6964
EL 6965
Kinloch
Kinloch
Kinloch
Kinloch
7 December 2023
13 December 2023
18 December 2023
18 December 2023
6 December 2029
12 December 2029
17 December 2029
17 December 2029
854
990
555
785
25%
25%
25%
25%
ELA 2557
Laloki
N/A (refused)
N/A (refused)
126
N/A
Tenement
Project
Location
EL 6141
Elizabeth Creek
EL 6518
Papua New
Guinea
SA
SA
SA
SA
Papua New
Guinea
Application Date
16 November 2017
3
Tenure is adjacent to Elizabeth Creek but has not been formally integrated into the broader Elizabeth Creek Project.
Note tenement transfer is ongoing as at current time
5 Note tenement transfer is ongoing as at current time
4
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
Tenements are held in a 70:30 split between Coda
Minerals and Torrens Mining Ltd, a wholly owned
subsidiary of Coda Minerals, resulting in effective
100% control by Coda Minerals.
Held 100% by Coda Minerals.
Held 100% by Coda Minerals.
Coda is currently engaged in a Farm-in to the
Cameron River project and has the option to earn
up to 80% ownership by spending $2 million. The
company has reached the threshold for 51%
ownership under the Agreement.
Held by wholly owned subsidiary Torrens Mining
Ltd
Held by wholly owned subsidiary Torrens Mining
Ltd
Held by wholly owned subsidiary Torrens Mining
Ltd
Held in a 25:75 split with Boss Energy
Application by wholly owned subsidiary Torrens
Mining
During the quarter, Coda announced together with Boss Energy, the successful application for a package of four highly
prospective tenements covering the Cambrian-Ordovician Delamerian Orogen basement rocks and the overlying
Cenozoic Murray Basin sediments in eastern South Australia. The tenure, which has since been formally granted, has
been dubbed the “Kinloch Project” by both companies, with the details specified in Table 1.
The tenure, awarded through the competitive Exploration Release Area (ERA) process will be held in 75:25 ownership,
with Coda holding 25%. However, Boss and Coda have agreed to progress a mineral rights sharing arrangement, under
which Coda will be entitled to 100% of the base metal rights while Boss will be entitled to 100% of the uranium rights on
the tenements. It is expected that the parties will enter into a mineral rights sharing agreement on customary terms, with
Coda to focus on the copper and base metal potential and Boss to focus on the uranium potential as part of regional
growth strategy.
2.2 Elizabeth Creek Copper-Cobalt Project Update
Elizabeth Creek Copper Cobalt Project Scoping Study
Ore Sorting
On the 5th of October6, Coda released details of its assessment of the applicability of XRF ore sorting to the Emmie Bluff
deposit. The work strongly indicated the suitability of the Emmie Bluff ore body for the technology and suggested it could
effectively sort and improve the grade prior to crushing. It is expected to be particularly useful in a scenario wherein
Emmie Bluff is mechanically cut rather than mined through drill and blast methodologies. Further work is required before
this technology can be fully integrated into the Company’s Elizabeth Creek Scoping Study.
During the quarter, Coda continued optimisation of the previously released Scoping Study into the Elizabeth Creek
Scoping Study, focussing on areas such as reagent optimisation, underground mining methods, ore sorting and more. The
results of some of these studies were released during the quarter, with the updated Scoping Study released to market
on 30th January 2024 (See “Events Subsequent to Quarter End", below).
IOCG Exploration
On the 3rd of October7, Coda announced a new geophysical interpretation of the Emmie IOCG prospect following a major
geophysical review and modelling exercise by Coda’s technical team and geophysical consultants Mira Geoscience and
NewGen Geo.
The review principally consisted of a synthesis of recent and historical data, focused primarily on drill results, 2D seismic
and Coda’s recent close-spaced gravity survey 8, as well as historic and recent magnetotelluric (MT), Ambient Noise
Tomography (ANT), density, petrophysics and other data.
The new model refines Coda’s existing hypothesis for the Emmie IOCG mineralising event, which proposed that low
pressure copper rich fluids moving up conduits are capped by granite thrust sheets. This forces the mineralising fluids to
move through the sub-horizontal permeable strata within the Wallaroo Group resulting in a series of stacked horizontal
lodes which extend up to several hundred metres away from the structures.
The new model suggests that a pair of North to NNE striking low angle thrust faults dipping to the east and plunging
slightly to the north are the most likely controlling structures and are associated with the highest density material in the
area. The model developed helps explain the structural controls underpinning the Emmie IOCG mineralisation and offers
valuable explanatory and predictive power.
6
Please see “Underground Ore Sorting Success Enhances Emmie Bluff”, available at https://www.codaminerals.com/wpcontent/uploads/2023/10/2023101-1.pdf
7 For full details, please see “Updated Geological Model Transforms IOCG Understanding”, available at https://www.codaminerals.com/wpcontent/uploads/2023/10/2023101.pdf
8
Completed in April of 2023. For details, see “Major Emmie IOCG Gravity Survey Completed”, released to the market on 5 April 2023 and available at
https://www.codaminerals.com/wp-content/uploads/2023/04/20230405_COD_ASX-ANN_Major-Emmie-IOCG-Gravity-SurveyCompleted_VRelease.pdf
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
The review identified that drilling to date has been focussed principally in the southern third of a ~1.8km long region
defined by basement elevation, gravity anomalism and interpreted structures. Due perhaps to the plunge of the faults,
basement elevation is lost at this point, but there is strong evidence from other indicators including historical drill results
that the trend continues at least to the tenement boundary and beyond, resulting in a total prospective corridor of
between of 2.5 and 3km.
Under this exploration model, additional IOCG mineralisation is anticipated to be found where permeable strata (as
previously defined in drilling) interact with the two identified mineralising structures. Figure 1 provides an example,
showing the approximate anticipated spread of nominal flat-lying permeable strata and the known faults. Beyond lateral
extension however, the model also suggests scope for expansion down-dip, which is supported by deeper mineralisation
known from historical holes 9.
Figure 1 Under the new model, high priority target zones are identified at the interaction between permeable flat lying strata within
the Wallaroo and one of the two primary identified faults. High density material serves as an effective proxy for haematite, which
provides the redox conditions for copper and gold to drop out of solution and concentrate.
2.3 Future Work Programme
Coda is currently progressing low-cost, high impact studies which have the potential to support further updates to the
scoping study. Per the recently released Update to the Elizabeth Creek Scoping Study, proposed or ongoing work
includes:
•
•
Assessment of the viability of paste fill (or similar) at Emmie Bluff to improve resource extraction ratio,
Assessing adjusted or alternative processing flowsheets, including additional work on tails leaching, to
optimise copper recovery,
9
E.g.. Historical drillhole MGD 55, located approximately 250m due east of mineralisation encountered in drillhole DD21EBD0002W3, where
mineralised (>1%Cu) intercepts start approximately 80m lower in the sequence, in line with the dip of the lower fault.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
•
•
Additional investigation into opportunities for concentrate sales on a larger scale (i.e. beyond Phase 1),
Exploration for additional tonnes, particularly in the vicinity of the Emmie Bluff Mineral Resource, where
numerous drill targets have been defined, principally by geophysics; and
Outside of the Elizabeth Creek project, the Company will undertake field work at its Cameron River project in Queensland
including mapping, soil sampling and re-assay of drill results to reassess the Uranium potential of the project.
3. Corporate
ESG Reporting – Quarterly Highlights
On the 11th of October10, in line with its commitment to high levels of environmental and social governance, Coda initiated
stand-alone ESG reporting with the release of its first standalone Sustainability Report.
Planet – Climate Change
In line with Coda’s commitment towards greater environmental accountability, Coda has commenced tracking and
reporting Scope 1 and Scope 2 greenhouse gas emissions in line with the GHG protocol.
Greenhouse Gas Emissions
Total Greenhouse Gas Emissions (tCO2-e)
Jul-Dec 2023
Total emissions
11.58
Scope 1 emissions
9.37
Scope 2 emissions
2.21
Scope 1 greenhouse gas (GHG) emissions refer to direct GHG emissions. They are comprised of fuel use and on-site
electricity generation. The Scope 1 emission factors applied are standard factors consistent with EPA’s Emission Factors
for Greenhouse Gas Inventories.
Scope 2 GHG emissions refer to indirect GHG emissions from the purchase of electricity from third parties. Scope 2
emissions have been calculated using the market-based method. The Scope 2 emission factors applied are standard
factors consistent with the Department of Environment and Energy, Australian National Greenhouse Accounts and the
National Greenhouse Accounts Factors, August 2023.
It's important to note that the data has not undergone third-party review.
Planet – Nature Loss
Coda initiated a dust monitoring study at its Elizabeth Creek site early this financial year, and the program remains
ongoing. The data collected will feed into environmental studies that are set to commence during the Pre-Feasibility
Study (PFS).
10
Please see “Sustainability Report 2023”, available at https://www.codaminerals.com/wp-content/uploads/2023/10/2023101-1.pdf
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
Finance & Use of Funds
Pursuant to ASX Listing Rule 5.3.2, the Company confirms that there were no mining production and development
activities during the quarter by the Company.
Total cash outflow from operating activities for the quarter was $0.9 million. This included $0.5 million in exploration and
evaluation expenditure and interest received of $26k, with the remaining expenditure was attributed to corporate and
administration costs. Of the remaining expenditure, $69k was for Directors’ fees paid during the period (refer Appendix
5B 6.1).
Coda expects the current level of net operating cash outflows to continue to decrease in the short term, as the Company
has implemented cost reduction measures to conserve cash. Future expenditure is not committed and remains at the
Company’s discretion. The Company is continuing to actively investigate and advance funding options and has made
excellent progress to date, with significant inbound interest received from potential funding and strategic partners.
Coda ended the December 2023 Quarter with $1.9 million in cash and deposits.
4. Events Subsequent to Quarter-End
On 30th January 2024, Coda released an update to its Elizabeth Creek Copper-Cobalt Project Scoping Study, integrating
mechanical cutting as the principal underground mining method employed at the Emmie Bluff deposit as well as
improvements to the mineral processing flowsheet, a greater annual throughput and other changes. The updated study
delivered improved pre-tax NPV8 of approximately $735 million, an increase of $165 million or 29% over the March 2023
Study, with an IRR of 27% and an AISC of $1.60 USD/lb Cu after by-product credits.
For full details, please see “Scoping Study Update Delivers Materially Improved Economics”, released to the market on
30th January 2024, and available at https://www.codaminerals.com/wpcontent/uploads/2024/01/20240130_Coda_ASX-ANN_Scoping-Study-Update-Delivers-Materially-ImprovedEconomics_RELEASE.pdf
Coda received 17.64 Kali Metals Limited (“Kali”) shares for every Kalamazoo Limited (“Kalamazoo”) shares held following
the successful spin out of Kali from Kalamazoo.
This announcement has been authorised for release by the Board of Coda Minerals Ltd
Further Information:
Chris Stevens
Chief Executive Officer
Coda Minerals Limited
info@codaminerals.com
Media:
Nicholas Read
Read Corporate
nicholas@readcorporate.com.au
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Coda Minerals Ltd
ABN
Quarter ended (“current quarter”)
49 625 763 957
December 2023
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
Year to date
(6 months)
$A’000
-
-
(462)
(1,314)
(b) development
-
-
(c) production
-
-
(d) staff costs
(257)
(721)
(e) administration and corporate costs
(180)
(789)
-
-
26
68
(a) exploration & evaluation
1.3
Dividends received (see note 3)
1.4
Interest received
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
-
-
1.9
Net cash from / (used in) operating
activities
(873)
(2,756)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
(2)
(d) exploration & evaluation
-
-
(e) investments
-
-
(f)
-
(54)
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date
(6 months)
$A’000
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing
activities
-
(56)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
-
-
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
-
-
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
(30)
(50)
3.10
Net cash from / (used in) financing
activities
(30)
(50)
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
2,758
4,717
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(873)
(2,756)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
-
(56)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
(30)
(50)
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
4.5
Effect of movement in exchange rates on
cash held
4.6
Cash and cash equivalents at end of
period
5.
Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
5.2
Current quarter
$A’000
Year to date
(6 months)
$A’000
-
-
1,855
1,855
Current quarter
$A’000
Previous quarter
$A’000
1,855
2,758
Call deposits
-
-
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
1,855
2,758
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
69
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
Current quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8.
Estimated cash available for future operating activities
8.1
Net cash from / (used in) operating activities (item 1.9)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(873)
8.4
Cash and cash equivalents at quarter end (item 4.6)
1,855
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
1,855
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
2.12
-
$A’000
(873)
-
-
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: N/A
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
31 January 2024
Authorised by: The Board of Coda Minerals Ltd
(Name of body or officer authorising release – see note 4)
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.
ASX Listing Rules Appendix 5B (17/07/20)