JUNE 2026
QUARTERLY ACTIVITIES REPORT
Elizabeth Creek advances towards key development decisions.
HIGHLIGHTS
Elizabeth Creek – Copper-Silver Project – Key PFS Data Delivered
- PFS foundations in place. Data delivered during the quarter is now being used to advance
resource definition, integrated mine planning and processing pathway selection at
Elizabeth Creek.
- LiDAR model unlocks parallel work1. A 480km² high-accuracy terrain model has been
delivered for mine, infrastructure, environmental and approvals design.
- Approvals pathway defined2. The final Scoping Report was gazetted after quarter end,
fixing the project-specific work programme towards a Mining Lease Application.
- Hydrogeological drilling underway3. A six-bore, ~1,400m programme will inform water,
mine design and approvals; one bore also follows up mineralisation outside the Emmie
Bluff MRE.
- Environmental baseline advanced4. Surveys found no groundwater-dependent
ecosystems likely to be affected, a positive approvals input.
Near-Term News Flow and Catalysts
- Updated resource and integrated mine plan. Final geotechnical inputs will enable the
MRE and integrated design across two open pits and the Emmie Bluff underground mine.
- Processing pathway selection. Leach, cobalt and flotation test work will drive the PFS
flowsheet trade-off.
- New exploration exposure at Oakden. Shallow RC drilling is planned after the
hydrogeological programme to test a new open-pit target.
Corporate
- Funding strengthened. Tranche 1 of the oversubscribed $6.7 million placement raised
$4.7 million before costs at $0.13 per share.
- Strong quarter-end cash position. Cash of $10.77 million at 30 June supports the PFS and
exploration. Additional $2 million cash expected subject to Tranche Two approval in early
August 2026.
- Key value milestone ahead. 100%-owned Elizabeth Creek provides direct exposure to a
large-scale copper-silver project targeting a Q1 2027 PFS in Tier-1 South Australia.
CONTENTS
Overview 1.0
Projects & Assets 2.0
Tenement Schedule 2.1
Elizabeth Creek
Copper Project
Update
2.2
Corporate 3.0
Finance &
Use of Funds
3.1
Upcoming and
Subsequent Events
4.0
Events Subsequent
to Quarter End
4.1
Near-Term
Catalysts and
Development
Activities
4.2
Appendix 1 5.0
ASX RELEASE
2026
ASX:COD
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
1. Overview
Discussing the quarter, Coda Minerals Chair, Keith Jones, said: "During the June quarter, Coda moved Elizabeth Creek
beyond data collection in several important areas and into the next phase of project definition. The LiDAR terrain model
is now supporting design across the site, environmental field work has advanced, and the final Scoping Report was
gazetted shortly after quarter end, giving the Project a clear framework for the approvals work ahead.
"What matters for shareholders is that these are not isolated activities. Each removes uncertainty or unlocks the next
decision: hydrogeological drilling informs water management and mine design; geotechnical results feed the updated
resource and integrated mine plan; and metallurgy will determine the preferred processing route. Together they build
confidence in the development case that the PFS is intended to demonstrate.
"There is also meaningful news flow ahead. Hydrogeological drilling is underway, Oakden exploration drilling is planned
to follow, and the resource, mine planning and metallurgical programmes are progressing towards important outputs.
"The oversubscribed placement and our $10.77 million quarter-end cash position, with another $2 million expected follow
in early August, will allow Coda to pursue this work from a position of strength. Elizabeth Creek remains a large-scale,
100%-owned copper-silver asset in a proven South Australian mining jurisdiction, and the Board believes the coming
milestones can further demonstrate its strategic and commercial value."1234
Figure 1: Hydrogeological drilling ongoing at Windabout subsequent to quarter end.
1
Please see ASX Announcement “Key Engineering Data Delivered for Elizabeth Creek PFS”, released on 13 July 2026.
2
Please see ASX Announcement “Elizabeth Creek Approvals Milestone Achieved”, released on 22 July 2026.
3
Please see ASX Announcement “Hydrogeological Drilling Starts at Elizabeth Creek”, released on 23 July 2026.
4
Please see ASX Announcement “Critical On-Ground Studies Begin at Elizabeth Creek”, released on 18 May 2026.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
2. Projects & Assets
2.1 Tenement Schedule
In accordance with ASX Listing Rule 5.3.3, Coda provides the following information about its tenements for the quarter
ended 30 June 2026.
Table 1 Coda tenement schedule
Tenement Project Location Grant Date Expiry Date
Area
km2
Ownership
EL 6141 Elizabeth Creek SA 29 October 2017 28 October 2028 47 100% Tenements are held in a 70:30 split
between Coda Minerals and Torrens
Mining Ltd, a wholly owned subsidiary of
Coda Minerals, resulting in effective
100% control by Coda Minerals.
EL 6518 Elizabeth Creek SA 25 March 2020 24 March 2031 363 100%
EL 6265 Elizabeth Creek SA 7 October 2018 6 October 2029 291 100%
EL 6945
Elizabeth
Creek5 SA 17 October 2023 16 October 2029 73 100%
Held 100% by Coda Minerals.
EPM 27042 Cameron River Queensland 10 October 2019 9 October 2029 22.4 100%
EPM 27053 Cameron River Queensland
14 February
2020
13 February
2030
12.8 100%
EL 6962
Kinloch SA 7 December
2023
6 December
2029
854
25% Held in a 25:75 split with Boss Energy.
Coda has 100% base metals rights for the
ground.
EL 6963
Kinloch SA 13 December
2023
12 December
2029
990
25%
EL 6964
Kinloch SA 18 December
2023
17 December
2029
555
25%
EL 6965
Kinloch SA 18 December
2023
17 December
2029
785
25%
2.2 Elizabeth Creek Project Update
During the quarter, Coda advanced multiple on-ground and engineering workstreams supporting the Elizabeth Creek Pre-
Feasibility Study (“PFS”) for its 100%-owned Elizabeth Creek Copper-Silver Project in South Australia.
Major PFS Field Programmes
Hydrogeological Drill Programme
Coda appointed an experienced hydrogeological drilling contractor and finalised the design of a dedicated
hydrogeological drilling programme, which commenced subsequent to quarter end6. The programme comprised three
production bores — two at Emmie Bluff and one at Windabout — together with three monitoring bores, designed to
assess water drawdown impacts across the strata likely to be affected by future mining. No drilling was planned at MG14,
reflecting the strength of existing historical hydrogeological data at that deposit.
Deeper monitoring holes were designed for assessment via vibrating wire piezometers, with shallower holes assessed
through direct dipping. One of these monitoring bores has been designed with a secondary exploration objective – it is
located approximately 300m NW of weakly mineralised Tapley Hill Formation material encountered in 2025.7 This
mineralisation falls outside the current Emmie Bluff Mineral Resource boundary, and may represent currently
unrecognised additional mineralisation.
5
Tenure is adjacent to Elizabeth Creek but has not been formally integrated into the broader Elizabeth Creek Project.
6
Please see ASX Announcement “Hydrogeological Drilling Starts at Elizabeth Creek”, released on 23 July 2026.
7
DD25EB0038 intersected a sub-economic intercept of mineralised Tapley Hill Formation (0.76m @ ~0.81% Cu from 435.6m. For full details, including
JORC Table 1, please see “Material Uplift in Copper and Silver Recoveries”, released to the market on 26 Jun 2025 and available at
https://codaminerals.com/announcements/7023903
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
Environmental and Ecological Surveys8
Following rain, the Company took the opportunity to carry out environmental and ecological surveys across the broader
project area during the quarter. Importantly, no groundwater-dependent ecosystems were identified as likely to be
impacted by proposed mining activities — a result that may help simplify future groundwater and environmental
approvals processes.
Airborne Lidar survey completed9
A 480km² fixed-wing airborne LiDAR survey was flown over the Project during the June quarter, covering all known
resources together with proposed infrastructure corridors and development areas. The survey comprised a series of
north–south aligned traverses flown at just under 5,000 feet, delivering a digital terrain model with 10cm vertical
accuracy. Both the processed terrain model and the associated high-resolution imagery were delivered subsequent to
quarter end, and are now being used across engineering, mining, environmental and approvals studies, providing a
common, highly accurate engineering base for mine planning, infrastructure layout, civil engineering, TSF design, waste
dump planning and drainage studies. High resolution imagery will also be utilised in heritage and environmental studies
going forward.
Elizabeth Creek PFS: Other
Metallurgy
Flowsheet development continued to advance through the final stages of chloride leaching test work, ahead of detailed
process engineering. In parallel, the Company commenced a new round of flotation test work to evaluate potential
improvements in flotation performance, with a final trade-off study between the chloride leach and flotation processing
routes to follow completion of both programmes.
Mine planning, Mineral Resource Estimation and infrastructure
Mine planning and the updated Mineral Resource Estimate continued to progress in parallel, pending final independent
geotechnical laboratory results required for both workstreams. The non-process infrastructure engineering work package
was awarded during the quarter and is progressing to schedule, while TSF engineering also continued to progress.
8
Please see ASX Announcement “Critical On-Ground Studies Begin at Elizabeth Creek”, released on 18 May 2026.
9
Please see ASX Announcement “Key Engineering Data Delivered for Elizabeth Creek PFS”, released on 13 July 2026.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
Figure 2 Production bore locations at Emmie Bluff and Windabout. Monitoring bores will be situated on the same cleared pads within 50m of the associated production bore.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
3. Corporate
3.1 Finance & Use of Funds
Pursuant to ASX Listing Rule 5.3.2, the Company confirms that there were no mining production and development
activities during the quarter by the Company.
The Company incurred total cash outflow from operating activities of $2.55 million for the quarter ended 30 June 2026.
The exploration and evaluation expenditure for the pre-feasibility study included final drilling expenditure from the Q1
quarter, site costs and technical advisor fees for various PFS workstream which totalled $2.26 million. The quarterly
corporate costs included annual compliance costs, consultants, investor relations costs and general IT and office expenses
of $0.27 million. Payments to staff (after allocation of costs to exploration expenditure) amounted to $0.12 million. Coda
received $70k in interest on cash balances during the quarter.
During the quarter ended 30 June 2026, a total of $157k was paid to the Directors of the Company including the payment
of all superannuation amounts for the quarter. Please refer to Section 6.1 of the Appendix 5B below.
The Company issued 36,153,847 fully paid ordinary shares at an issue price of $0.13 per share to raise $4,700,000 (before
costs) as part of a Tranche 1 placement to sophisticated investors in early June 202610. The placement was oversubscribed
and included one listed option for every 4 shares subscribed. The options are subject to shareholder approval at a general
meeting on 3 August 2026.
The Company ended the quarter with $10.77 million in cash and cash equivalents after completing the work on a number
of PFS milestones during the quarter and continuing to progress the pre-feasibility study on the Company’s flagship
Elizabeth Creek project.
Although the Company ended the quarter with cash and cash equivalents of $10.77 million. This balance excludes a
further approximately $2.0 million to be raised under Tranche 2 of the placement, subject to shareholder approval at the
General Meeting on 3 August 2026.
4. Upcoming and Subsequent Events
4.1 Events Subsequent to Quarter-End
Environmental approvals — Scoping Report gazettal11
A significant milestone was reached in the weeks following quarter-end with the gazettal of the Project's Scoping Report
by the South Australian Department for Energy and Mining ("DEM"). This followed an extensive period of technical and
regulatory work to define the project-specific scope of environmental studies and data collection required ahead of a
Mining Lease Application in South Australia.
With the Scoping Report now gazetted, it forms a binding agreement between Coda and the State Government,
establishing a fixed and transparent regulatory framework for the environmental studies to be completed as the Project
advances. Securing this outcome reflects a substantial and sustained body of work by the Company and marks the start
of the formal environmental approvals pathway.
Hydrogeological drilling commenced12
Subsequent to quarter end, Coda mobilised a rig to Elizabeth Creek and commenced hydrogeological drilling at the
Windabout and Emmie Bluff prospects. The programme comprises six bores for an estimated 1,400 metres: one
production bore and one monitoring bore at Windabout, and two production bores and two monitoring bores at Emmie
10
Please see ASX Announcement “$6.7m Placement to Expedite PFS Workstreams”, released on 1 June 2026.
11
Please see ASX Announcement “Elizabeth Creek Approvals Milestone Achieved”, released on 22 July 2026.
12
Please see ASX Announcement “Hydrogeological Drilling Starts at Elizabeth Creek”, released on 23 July 2026.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
Bluff. Production bores will support aquifer pump testing, while monitoring bores will track groundwater response,
feeding the regional hydrogeological model underpinning the PFS.
Results from this test work will inform geotechnical design, mine dewatering and depressurisation planning, the overall
site water balance, and the Project's environmental approvals and Mining Lease Application pathway. In addition, one of
the Emmie Bluff bores is located approximately 300 metres north-west of diamond drillhole DD25EB0038, in which the
Company previously reported copper mineralisation in the Tapley Hill Formation well outside the footprint of the existing
Emmie Bluff MRE.
While these bores are being drilled for hydrogeological purposes and are not explicitly designed as exploration holes, drill
cuttings and any recovered core will be geologically logged, providing an incidental opportunity to gather further
information from an area the Company considers prospective for further mineralisation13.
4.2 Near-Term Catalysts and Development Activities
Priority during the upcoming months will be given to the ongoing and upcoming hydrogeological and exploration drill
programmes, as well as to completing the ongoing data collection phase of the PFS, and fully transitioning to the trade-
off and study phase.
Metallurgy
Metallurgical testwork is expected to continue in the September quarter.
Variability testwork on the base-case whole-ore chloride leaching flowsheet is ongoing, alongside cobalt tails flotation
testwork, with a final assessment of an alternative flotation processing pathway currently underway at laboratories in
Adelaide. Completion of this work will inform a final trade-off study between the chloride leach and flotation processing
routes, a key determinant of the PFS-level flowsheet. Detailed comminution studies are also ongoing across all three
major deposits (MG14, Windabout and Emmie Bluff).
Mine design, geotechnical and infrastructure
Geotechnical information continues to be received and incorporated into mine design and planning, with final
independent laboratory results expected to allow completion of both the mine plan and the updated Mineral Resource
Estimate. Tailings Storage Facility design is also continuing to progress, drawing on the recently delivered LiDAR terrain
model, ongoing geotechnical inputs and the detailed site-selection work commenced during the quarter.
Oakden exploration
The hydrogeological programme at Windabout and Emmie Bluff is expected to take several weeks to complete. On
completion, the rig will be relocated to the Oakden prospect — a new, shallow open-pit exploration target in the southern
portion of the Elizabeth Creek Project — to commence a follow-up exploration programme of approximately 5–6 RC
drillholes for up to 400 metres. The Company will release a further announcement detailing the targeting rationale for
Oakden in due course.
Concurrently with the Oakden programme, Coda will undertake aquifer pump testing to determine groundwater flow
and recharge rates, informing a full site water balance. This will determine next steps in the field: which may include a
further programme later in the year to define available water resources and plan a production borefield, or, if water risk
is assessed as low, this work may instead be deferred into the Definitive Feasibility Study stage.
Environmental approvals
Following gazettal of the Scoping Report, the Company will progress the environmental studies and data collection
defined under that agreement, working toward the Environmental Impact Assessment as the next major milestone on
the pathway to a Mining Lease Application.
13
DD25EB0038 intersected 0.76m of mineralised Tapley Hill Formation black shale at approximately 0.81% Cu from 435.6m. For full details, including
JORC Table 1, please see “Material Uplift in Copper and Silver Recoveries”, released to the market on 26 Jun 2025 and available at
https://codaminerals.com/announcements/7023903 The Company cautions that the mineralisation previously reported in DD25EB0038 was of sub-
economic thickness, that these bores are not intended primarily to test for mineralisation, and that there is no assurance that any mineralisation will
be encountered.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
Other Key Workstreams
A contractor has been selected to advance Non-Process infrastructure studies, and preliminary process engineering is
expected to commence as soon as data is available. This may include preliminary work on specific circuits, such as
crushing and grinding, prior to the selection of a final processing methodology.
The Company continues to target a delivery of the Elizabeth Creek PFS in Q1 2027, consistent with previous guidance.
--
This announcement has been authorised for release by the Board of Coda Minerals Ltd
Further Information:
Chris Stevens
Chief Executive Officer
Coda Minerals Limited
info@codaminerals.com
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
5. Appendix 1
5.1 Elizabeth Creek Mineral Resources
Table 2 Aggregated Mineral Resources at Elizabeth Creek
OPEN PIT Proposed Tonnage Cut-off Copper Cobalt Silver Zinc Copper Equivalent
Resource Category Type Mining Mt Grade Grade Contained Grade Contained Grade Contained Grade Contained Grade Contained
Method (% Cu) Metal (t) (ppm Co) Metal (t) (g/t Ag) Metal (Moz) (ppm Zn) Metal (t) (% CuEq) Metal (t)
MG14 Indicated Zambian Open Pit 1.8 0.5% CuEq 1.2% 22,700 330 600 14 0.8 1.7% 30,600
Cattle Grid South Inferred Breccia Open Pit 5.8 0.2% Cu 0.6% 36,000 120 700 3.5 0.7 684 4000 36,00014
Windabout Indicated Zambian Open Pit 17.7 0.5% CuEq 0.8% 136,100 490 8700 8 4.6 1.4% 249,100
Sub Totals Indicated Zambian Open Pit 19.5 0.5 CuEq 0.8% 158,800 480 9300 8.5 5.4 1.4% 316,000
(Open Pit) Inferred Breccia Open Pit 5.8 0.2% Cu 0.6% 36,000 120 700 3.5 1 684 4,000
UNDERGROUND Proposed Tonnage Cut-off Copper Cobalt Silver Zinc Copper Equivalent
Resource Category Type Mining Mt Grade Grade Contained Grade Contained Grade Contained Grade Contained Grade Contained
Method (% Cu) Metal (t) (ppm Co) Metal (t) (g/t Ag) Metal (Moz) (ppm Zn) Metal (t) (% CuEq) Metal (t)
Indicated Zambian Underground 37.5 1% CuEq 1.3% 485,000 590 22,000 17 20.6 1800 66000 1.9% 715,000
Emmie Bluff Inferred Zambian Underground 2.7 1% CuEq 0.9% 46,000 280 1,000 12 1.1 1700 5000 1.3% 36,000
Sub Total
(Underground)
Combined Zambian Underground 40.2 1% CuEq 1.3% 511,000 570 23,000 16.8 21.7 1700 70000 1.9% 751,000
Project Wide Total15
65.5 Mt 725,800t Contained Cu 33,000t contained Co 28 Moz Contained Ag 75,000t Contained Zn16
1,067,000t contain CuEq
14
No Copper Equivalent was calculated for Cattle Grid South. Contained CuEq tonnes quoted in this column for Cattle Grid South consist of contained copper only.
15
Total figures have been aggregated purely for convenience and to contextualise the specific contribution of individual Mineral Resource Estimates to the overall project scale. Grades reported are tonnage-weighted
averages of the individual Mineral Resource Estimates. Coda notes that the total figure includes resources reported at varying cut-off grades, with varying estimation techniques, metallurgical properties and proposed
mining methods. Individual Mineral Resource Estimates should be considered individually. A total copper equivalent figure has not been disclosed as Coda does not believe it is currently appropriate to calculate a
copper equivalent for the Cattle Grid South Mineral Resource Estimate. Please see below sections Statement Regarding Metal Equivalent Calculations and Competent Persons Statement for full details on the calculation
of copper equivalents and links to original releases/CP statements. Figures have been rounded for simplicity.
16
No Zinc estimate was provided for the MG14 and Windabout deposits. This figure reflects the contained tonnage solely from Emmie Bluff and Cattle Grid South.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
5.2 Competent Persons’ Statements and Confirmatory Statement - Mineral Resource
Estimates
MG14 Indicated Mineral Resource: The information is extracted from the report entitled "Confirmation Statements
JORC" created on 26th October 2020 and is available to view at:
https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-02298915-
6A1003162&v=70bc033a22188bdfefb8a0b8ad3c24897ef2837d.
The company confirms that it is not aware of any new information or data that materially affects the information included
in the original market announcement and, in the case of estimates of Mineral Resources or Ore Reserves, that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to
apply and have not materially changed. The company confirms that the form and context in which the Competent
Person’s findings are presented have not been materially modified from the original market announcement.
Windabout Indicated Mineral Resource: The information is extracted from the report entitled "Confirmation Statements
JORC" created on 26th October 2020 and is available to view at:
https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-02298915-
6A1003162&v=70bc033a22188bdfefb8a0b8ad3c24897ef2837d.
The company confirms that it is not aware of any new information or data that materially affects the information included
in the original market announcement and, in the case of estimates of Mineral Resources or Ore Reserves, that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to
apply and have not materially changed. The company confirms that the form and context in which the Competent
Person’s findings are presented have not been materially modified from the original market announcement.
Emmie Bluff Mineral Resource: The information is extracted from the report entitled “Scoping Study Update Delivers
Materially Improved Economics" created on 30 January 2024 and is available to view at:
https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-02766550-6A1191314.
The company confirms that it is not aware of any new information or data that materially affects the information included
in the original market announcement and, in the case of estimates of Mineral Resources or Ore Reserves, that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to
apply and have not materially changed. The company confirms that the form and context in which the Competent
Person’s findings are presented have not been materially modified from the original market announcement.
Cattle Grid South Mineral Resource: The information is extracted from the report entitled “Initial Copper Resource for
Cattle Grid South" created on 03 July 2024 and is available to view at:
https://cdn-api.markitdigital.com/apiman-gateway/ASX/asx-research/1.0/file/2924-02823989-
6A1214274&v=4015c7b87631faf94ecd96975272ff9ad5cb14c3.
The company confirms that it is not aware of any new information or data that materially affects the information included
in the original market announcement and, in the case of estimates of Mineral Resources or Ore Reserves, that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to
apply and have not materially changed. The company confirms that the form and context in which the Competent
Person’s findings are presented have not been materially modified from the original market announcement.
5.3 Listing Rule 5.19.2
In relation to any Production Target or any forecast financial information based on any Production Target quoted or
referenced in this announcement, the Company confirms that all material assumptions underpinning both the Production
Target and any forecast financial information continue to apply and have not materially changed.
The original ASX announcement released on 3 December 2024 relating to any Production Target or forecast financial
information derived from any Production Target referenced within this announcement can be found here.
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
5.4 Listing Rule 5.23.2
The Company confirms that it is not aware of any new information or data that materially affects the information included
in the original market announcements cited in this announcement and, in the case of estimates of Mineral Resources or
Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed. The Company confirms that the form and context in
which the Competent Person’s findings are presented have not been materially modified from the original market
announcement.
5.5 Statement Regarding Metal Equivalent Calculations
Metal Equivalent grades are quoted for one or more of the Emmie Bluff, Windabout and MG14 Mineral Resources, or for
exploration results considered by the company to be related directly to one of these Mineral Resources, in this
announcement.
For the Emmie Bluff Mineral Resource:
The Emmie Bluff Mineral Resource is reported as 40.2Mt @ 1.27% Cu, 569 ppm Co, 16.8 g/t Ag and 0.17% Zn (1.87%
Copper Equivalent (CuEq)) reported at a cut-off grade of 1% CuEq. The calculation of this metal equivalent is based on
the following assumptions.
Metal Coefficient Forecast Price Price Unit
Copper 0.8 $7,000 USD/Tonne
Cobalt 0.85 $55,000 USD/Tonne
Zinc 0.9 $2,100 USD/Tonne
Silver 0.85 $18.50 USD/Oz
Price assumptions used when calculating copper equivalent grades were based primarily on Consensus Economics
forecasts of metals, except for Cobalt, which was sourced via communication with subject matter experts. Metallurgical
assumptions used when calculating copper equivalent grades were based on a simple bulk float utilising rougher and
minimal cleaner/scavenger circuits. The produced a reasonably consistent mean recovery across most metals of between
approximately 83 and 94 percent. For simplicity, and to in part account for losses associated with less intensive cleaner
floats and losses to the hydromet plant, these figures were rounded down to the nearest 5%.
Application of these assumptions resulted in the following calculation of CuEq:
𝐶𝑢𝐸𝑞% = 𝐶𝑢% + 0.00068 × 𝐶𝑜 𝑝𝑝𝑚 + 0.337 × 𝑍𝑛 % + 90.3 ×
𝐴𝑔 𝑝𝑝𝑚
10000
For the Windabout and MG14 Mineral Resource:
The Windabout and MG14 Mineral Resource are reported at a cut-off grade of 0.5% CuEq as:
• Windabout: 17.67Mt @ 0.77% Cu, 492 ppm Co and 8 g/t Ag (1.41% CuEq)
• MG14: 1.83Mt @ 1.24% Cu, 334 ppm Co and 14 g/t Ag (1.84% CuEq)
The calculation of this metal equivalent is based on the following assumptions.
Metal Mining
Recovery %
Dilution % Recovery % Payability % Forecast Price Price Unit
Copper 0.9 0.05 0.6 0.7 $6,600 USD/Tonne
Cobalt 0.9 0.05 0.85 0.75 $55,000 USD/Tonne
Price assumptions used when calculating copper equivalent grades were based on recent historical metal prices at the
time of calculation (2018). Metallurgical assumptions are based on extensive metallurgical testwork undertaken on the
two deposits to 2018 across various potential flowsheets involving both floatation and leaching. Ag analyses in the
estimation and metallurgical testwork were considered insufficient at the time to include in the metal equivalent
calculation.