Elizabeth Creek Project Economics - Additional Information
Released
Released
Announcement PDF
6 Altona Street
West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
ELIZABETH
CREEK
10 March 2026
Elizabeth Creek Project Economics Strengthen on Price Update –
Appended Information
Coda Minerals Limited (ASX: COD, “Coda” or “the Company”) hereby re-releases the announcement made to ASX on
17 February 2026, “Elizabeth Creek Project Economics Strengthen on Price Update”.
The production target and mine schedule have been amended to remove solely Inferred material from the last two
years of the mine plan. Inferred Mineral Resources comprise approximately 0.03%, 0.03% and 5.42% of the contained
metal in the first three years, five years and the project’s entire operating life respectively. The viability of the
development scenario envisaged in the Scoping Study does not depend on the inclusion of Inferred Mineral Resources.
The Company has concluded that it has reasonable grounds for disclosing a production target which includes an amount
of Inferred Mineral Resources. There is a low level of geological confidence associated with Inferred Mineral Resources
and there is no certainty that further exploration work will result in the determination of Indicated Mineral Resources
or that the production target itself will be realised.
The Directors of Coda Minerals confirm that the technical, mining, processing, capital and operating cost assumptions
have been reviewed and, at the time of publication, remain appropriate and consistent with Scoping Study–level
accuracy (±35%), in line with the August 2025 Update referenced in this announcement.
Please refer to Pages 13 and 14 of this announcement for the updated mine schedule breakdown by classification.
--
This announcement has been approved for release by the board of Coda Minerals.
6 Altona Street, West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
Elizabeth Creek Project Economics Strengthen on Price Update
Significant price movements in copper and silver result in material uplift from August 2025 Scoping Study.
Highlights
• PROJECT ECONOMICS REEVALUATION: Material changes in both forecast and SPOT prices of copper and silver have
necessitated an update to the August 2025 Scoping Study.
• COPPER-SILVER BASE CASE: All work retains existing processing flowsheet offering a streamlined project using a
copper-silver base case. This provides exception upside to two high attractive mineral commodities.
• SIMPLIFIED PROJECT: Streamlined project using a copper-silver base case with cobalt offering attractive future upside.
This is expected to reduce commodity risk and strengthen the development case.
• PLANNED PRODUCTION: Estimated 454kt of copper and 20Moz of silver over the life-of-mine. Annual estimated
steady state production approximately 32ktpa copper, 1.4Mozpa silver.
• UPDATED PRICE ASSUMPTIONS: Copper price assumption updated to US$ 10,500/t from US$ 9,260/t; silver price
assumption updated to US$ 60/oz from US$ 30/oz. This remains materially below current SPOT prices1.
• PROJECT FINANCIALS: Estimated Pre-tax NPV(7) of approximately $2.25B and Internal Rate of Return (IRR) of 56%,
compares with a Pre-tax NPV(7) of ~A$1.29B and IRR of 39% in the 2025 Scoping Study1F
2.
• UPSIDE AT SPOT: At spot prices, the estimated Pre-tax NPV(7) increases to approximately $3.32B and the IRR to 74%.
Post-Tax NPV(7) of approximately $1.52B, IRR 43% (base case), rises to approximately $2.28B and IRR 57% at spot2
F
1.
• RAPID PAYBACK: Revised base case offers attractive 2.5 year payback period from first production.
• RAPID ADVANCEMENT: Revised copper-silver base case incorporated in currently ongoing Pre-Feasibility Study (PFS).
• WELL FUNDED: $11.25M cash in bank at end of December 2025 Quarter leaves Coda well-funded for advancing PFS
work.
Coda Minerals Limited (ASX: COD, “Coda” or “the Company”) is pleased to report revised economics for its flagship 100%-
owned Elizabeth Creek Copper-Silver Project in South Australia following material changes in the underlying pricing of copper
and silver since the most recent release of project economics in August 2025.
Economics Update – Elizabeth Creek Copper-Silver Project.
Coda Minerals Limited (ASX: COD, “Coda” or “the Company”) is pleased to provide an updated snapshot of the economics for
its 100%-owned Elizabeth Creek Copper-Silver Project in South Australia, reflecting material changes in copper and silver
prices since the Company’s most recent economics update released in August 2025.
1
Spot Prices at 11th
February 2026. Cu – $13,108 USD/t, Ag - $82 USD/Oz, FX – 0.71 AUD/USD. NB SPOT pricing is highly volatile and should not be used as
the basis for investment decisions.
2
Please see ASX Announcement “New Flowsheet Delivers Significant Cu-Ag Economic Uplift”, released to the market 28 August 2025, available at
https://codaminerals.com/announcements/7126651
ASX RELEASE
2026
Code: COD
10 March 2026 ASX:COD
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Why we are providing this update
Since the August 2025 Scoping Study update, global commodity markets have moved significantly. Over the past five months,
both copper and silver prices have increased materially, driven by a combination of supply constraints, strong demand
fundamentals and heightened market volatility. The Company has received numerous queries from shareholders regarding
the impact of these commodity price movements on the economics of the project, and has encountered public speculation
online regarding these impacts, and wishes to ensure full clarity for shareholders.
The August 2025 economics were based on commodity prices of US$9,260 per tonne for copper and US$30 per ounce for
silver. As at the date of this announcement, copper is trading at approximately US$13,108 per tonne and silver at
approximately US$82 per ounce. Silver pricing has risen to approximately $120 per ounce in January 2026.
While commodity prices can be volatile and may move down as well as up, recent price behaviour highlights both the strength
of longer-term fundamentals for copper and silver and the potential for significant price swings over time.
Scope and limitations of this update
Spot price scenarios are presented solely to illustrate price sensitivity and do not represent the Company’s long-term planning
assumptions or development basis. Project advancement decisions will be based on long-term consensus pricing, not short-
term market volatility.
Coda is currently advancing a Pre-Feasibility Study (PFS) for the Elizabeth Creek Copper-Silver Project and remains well funded,
with $11.25 million in cash at the end of the December 2025 quarter.
This announcement provides a Scoping Study–level Project Update. The Directors of Coda Minerals confirm that mining,
processing, capital and operating cost assumptions have been reviewed and that as at the time of publication, are appropriate
and consistent with a Scoping Study (+/- 35%) level of accuracy consistent with the August 2025 Update. 3 The Directors
confirm that all technical assumptions relating to the study continue to apply.
The Company considers it appropriate to provide this update because long-term price assumptions for both copper and silver
have shifted materially since August 2025, meaning previously published sensitivities are no longer representative of current
market conditions. By way of example, the prior silver sensitivity of ±20% from US$30/oz represented a range of US$24/Oz to
US$36/Oz, compared with the current spot price of approximately US$82/oz.
Please see below Appendix 1 for Listing Rule 5.19.2 and Listing Rule 5.23.2 statements
Updated project economics
The Elizabeth Creek Copper-Silver Project is planned as a long-life operation, producing approximately:
• 454,000 tonnes of copper, and
• 20.3 million ounces of silver over the life of mine.
Using conservative long-term price assumptions of:
• US$10,500/t copper (approximately 20% below current spot)
• US$60/oz silver (approximately 27% below current spot)
• AUD/USD exchange rate of 0.68
The updated estimated project economics are approximately:
• Post-tax NPV(7): $1.52 billion
• Pre-tax NPV(7): $2.25 billion
3 Please see ASX Announcement “New Flowsheet Delivers Significant Cu-Ag Economic Uplift”, released to the market 28 August 2025, available at
https://codaminerals.com/announcements/7126651
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
• Post-tax IRR: 43%
• Pre-tax IRR: 56%
At current spot prices, the indicative economics increase materially to approximately:
• Post-tax NPV(7): ~$2.28 billion
• Pre-tax NPV(7) ~$3.32 billion
• Post-tax IRR: ~57%
• Pre-tax IRR: ~74%
These SPOT figures are illustrative only and should be read in the context of market volatility and the Scoping Study–level
nature of this update. Project advancement decisions will be based on long-term consensus pricing, not short-term market
volatility.
Sensitivity to commodity prices
In selecting base-case price assumptions below current spot levels, the Company believes it has applied appropriately
conservative settings, informed by reputable long-term forecasts. The copper price assumption of US$10,500/t sits within
the range of long-term consensus forecasts published by major investment banks and industry analysts (generally US$9,500–
11,500/t). The silver assumption of US$60/oz reflects an average of long-term forecasts and structural supply deficit
expectations.
The Project demonstrates strong leverage to both copper and silver prices:
• Each US$1,000/t change in the copper price impacts base case NPV(7) by approximately $377 million
• Each US$10/oz change in the silver price impacts base case NPV(7) by approximately $165 million
Detailed sensitivities are provided in the body of this announcement. Shareholders are cautioned that commodity prices are
inherently volatile and can move down as well as up.
CEO commentary
Chief Executive Officer Chris Stevens said: “We’ve received a large number of enquiries from shareholders asking how recent
movements in copper and silver prices affect the value of Elizabeth Creek. This update is intended to answer those questions
clearly and transparently.
“What it demonstrates is the exceptional leverage the Project has to both copper and silver prices, while still showing very
strong economics using conservative long-term assumptions.
“At the same time, we are continuing to advance the Pre-Feasibility Study at pace. Drilling is materially complete, assays are
pending, and all major PFS workstreams are now underway.
“We believe the timing could not be better to be progressing Elizabeth Creek through advanced study stages, and we look
forward to providing shareholders with further PFS updates as the project continues to be de-risked.”
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Cautionary Statements
Cautionary Statement Regarding Metallurgical Testwork
The Company advises that the metallurgical results relied upon to generate this estimate are preliminary in nature and
based on early-stage testwork. While the testwork has been conducted and reported with due care, and while it is the
opinion of Coda’s technical experts and its metallurgical consultants that the laboratory results relied on for this
estimate are likely to be applicable to all the mineralogically and geologically similar deposits at Elizabeth Creek,
further work is required to confirm the applicability of these results across the broader Elizabeth Creek Project,
including additional variability testing at Emmie Bluff and assessment of applicability to the MG14, Windabout and
Cattlegrid South deposits. Investors are cautioned that these results are not definitive and should not be relied upon
as a basis for investment decisions. Further testwork and analysis will be undertaken during the ongoing Pre-Feasibility
Studies, and these tests are expected to provide greater confidence when estimating the economic potential of the
Project at PFS level. This test work will be required before any production or economic outcomes can be confirmed.
Cautionary Statement Regarding CAPEX and OPEX Estimates
The Company advises that the CAPEX and OPEX estimates presented in this announcement which underpin the
economic assessments, though they have been prepared with due care by suitably qualified experts to the standard of
a Scoping Study, are derived in part from modifications of Coda’s earlier CAPEX and OPEX estimates, first presented in
2022. This has been done to ensure direct comparability with earlier iterations of the Scoping Study, however it should
be noted changing underlying market conditions may mean that a full recalculation would produce different numbers
if undertaken from scratch. This work will be undertaken during upcoming Pre-Feasibility Studies, and this work is
expected to provide greater confidence when estimating the economic potential of the Project at PFS level. This work
will be required before any production or economic outcomes can be confirmed.
Cautionary Statement Regarding Use of Inferred Resources in Production Targets
Production targets are unchanged from the December 2024 Scoping Study8F
4 and include contributions from Inferred
Resources. Emmie Bluff Production Target includes 96% Indicated and 4% Inferred Resources, MG14 and Windabout
100% Indicated, Cattle Grid South 100% Inferred.
The Company has concluded that it has reasonable grounds for disclosing a production target which includes an
amount of Inferred Mineral Resources. There is a low level of geological confidence associated with Inferred Mineral
Resources and there is no certainty that further exploration work will result in the determination of Indicated Mineral
Resources or that the production target itself will be realised.
Inferred Mineral Resources comprise approximately 0.03%, 0.03% and 5.42% of the contained metal in the first three
years, five years and the project’s entire operating life respectively. The viability of the development scenario envisaged
in the Scoping Study does not depend on the inclusion of Inferred Mineral Resources.
Cautionary Statement Regarding Calculation Ore Reserves
The Scoping Study referred to in this report is based on low-level technical and economic assessments, and is
insufficient to support estimation of Ore Reserves or to provide assurance of an economic development case at this
stage, or to provide certainty that the conclusions of the Scoping Study will be realised.
4 Available at https://codaminerals.com/announcements/6690414
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Project Economic Modelling
The economics of the Elizabeth Creek Project have been re-modelled with updated base-case commodity price
assumptions. Material changes include:
- Copper Price (USD/t) – From $9,260 to $10,500
- Silver Price (USD/Oz) – From $30 to $60
Coda’s updated base-case commodity price assumptions have been derived in a variety of ways and checked against
comparable peer projects to ensure consistency with the broader market. The selected copper price of US$10,500/t
(US$4.76/lb) is below the six-month average LME price leading up to release of this study and is considered
conservative given the current market conditions.
All other relevant economic factors, including assumptions around foreign exchange rates, royalty rates, etc, and
technical factors, including recoveries, CAPEX and OPEX estimates, etc, remain as stated in the Company’s most recent
Scoping Study7F
5. The table below shoes the assumptions underlying the new base-case project economics.
Macroeconomic Assumptions Table
DISCOUNT RATE REAL% 7.0%
EXCHANGE RATE USD:AUD 0.68
FEDERAL CORPORATE TAX RATE % 30%
SAROYALTY RATES
REFINED
PRODUCT
3.5%
COPPER PRICE USD/T $10,500
SILVER PRICE USD/OZ $60
ZINC PRICE USD/T $2,700
5
Coda’s last Scoping Study Update, released to the market on 28 August 2025, is available at
https://codaminerals.com/announcements/7126651
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Project Economic Summary
Area Measure Unit
Previous
Study
Updated
Base Case
Spot
Price[1]
COMMODITY
PRICES
Copper (USD/t) 9,260 10,500 13,108
Silver (USD/Oz) 30.00 60.00 82.00
FX (USD:AUD) 0.68 0.68 0.71
REVENUE
Revenue A$M 7,264 8,979 10,889
Copper % 85% 78% 77%
Silver % 12% 20% 21%
Zinc % 3% 2% 2%
FINANCIALS
Pre-Tax Net Cash Flow A$M 2,397 4,040 5,873
Pre-Tax (NPV7) A$M 1,289 2,247 3,322
Pre-Tax IRR % 39% 56% 74%
Total Capital Payback Years 3.25 2.50 1.75
Post-Tax Net Cash Flow A$M 1,692 2,841 4,129
Post-Tax (NPV7) A$M 855 1,521 2,278
Post-Tax IRR % 30% 43% 57%
PRODUCTION
Mine Life Years 15.5
Ore Process Rate Mtpa 3
Feed from Indicated Resource % 87%
Feed from Inferred Resource % 13%
Copper Produced – Total Kt 454
Silver Produced – Total Moz 20.3
Copper – Steady State Average[2]
Ktpa 31.9
Silver – Steady State Average[2]
MOzpa 1.4
CAPITAL
Pre-Production Capital A$M 472
Post-Production Capital A$M 143
Total Capital A$M 615
Total Financing Requirement A$M 478
OPERATING
C1 Cost USD/lb Cu 1.90 1.30 0.97
All In Sustaining Cost[2]
USD/lb Cu 2.15 1.60 1.33
[1]
Spot Prices as of 11th
February 2026.
[2]
Steady State Average is calculated from year 5 to year 15
[2]
All-In Sustaining Cost (AISC) includes all mining, processing, tailings management, transport including freight, sustaining capital, royalties
& G&A costs
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Sensitivity Analysis
Sensitivity analysis was carried out to determine the impact of various factors on the Project’s financial performance.
The graph below illustrates how the estimated base case NPV ($2.249B) varies when each of the key inputs increases
or decreases by 20%, with the exception of the discount rate, which was varied between 6.5% and 12%, reflecting a
more realistic market range.
Sensitivity analysis on copper and silver prices has been excluded from this tornado analysis and has been assessed
separately, due to the significant volatility and material price movements experienced over the past six months.
$500 $1,500 $2,500 $3,500
Exchange Rate
Discount Rate
Mining OPEX
Processing OPEX
CAPEX
Sensitivity Analysis
Figure 1 Project pre-tax NPV sensitivity to key variables. Please note that the above chart does not account for
correlation between variables and the model remains ceteris paribus.
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Coda has modelled the Project’s sensitivity to a range of potential copper and silver price scenarios, spanning from a
low case of US$9,000/t12F copper (12-month low) and US$20/Oz silver, through to current spot prices (in bold) and
upside case for both commodities, see Figure 2.
Sensitivity has been independently modelled for movements in both copper and silver prices. On a standalone basis,
the analysis indicates that, on average, a US$10/oz increase in silver price results in an increase in pre-tax NPV7 of
approximately A$165 million, while a US$1,000/t increase in copper price results in an increase in pre-tax NPV7 of
approximately A$377 million.
Although silver prices have increased by a materially greater factor than copper prices over the past six months, the
Project’s revenue remains predominantly driven by copper.
Under the updated commodity price forecasts, copper contributes approximately 78% of lifetime project revenue
(compared to 85% using previous commodity price assumptions) while silver remains an important by-product,
accounting for approximately 20% (compared to 12% previously). If modelled at current spot prices, copper accounts
for approximately 77% of total revenue, with silver contributing approximately 21%.
Even at a highly conservative copper price of US$8,000/t, silver prices would need to exceed approximately US$180/oz
before silver would exceed 50% of lifetime project revenue. Under the current assumed copper prices of US$10,500,
silver would need to exceed US$240/Oz to achieve a 50% revenue share.
Figure 2 Project pre-tax NPV7 sensitivity to changes in copper and silver prices at FX Rate USD:AUD 0.68.
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Project CAPEX
Total project CAPEX has remained unchanged to the August 2025 Scoping Study update. Net project CAPEX is
estimated at A$615 million under the current assumptions.15F
6 A detailed breakdown of project CAPEX is provided as
Table 1, below.
Table 1 Elizabeth Creek CAPEX cost breakdown
PRE-PRODUCTION CAPITAL EXPENDITURE A$M
Underground Mining 37
Process Plant 285
Camp 31
Site Infrastructure 52
Tailings Storage Facility 22
Contingency 42
Owners Costs 3
Total Pre-Production Capital Expenditure 472
Capital Intensity16F
7
, Steady-State Annual, (USD/t Cu) $10,065
Capital Intensity, Lifetime, (USD/t Cu) $707
POST-PRODUCTION CAPITAL EXPENDITURE A$M
Underground Mining 143
Process Plant 0
Total Post-Production Capital Expenditure 143
Total Capital 615
Following review by the Company’s board and management, the Company believes that capital cost estimates are
appropriate for a Scoping Study with a margin of error estimated at +/- 35%.
Coda is currently undertaking a Pre-Feasibility Study into the Elizabeth Creek Project, which will include a detailed
engineering design study intended to produce more up to date and accurate capital cost estimates. CAPEX
sensitivity analysis is provided in the “Sensitivity Analysis” section, above.
6
Please see Cautionary Statement Regarding CAPEX and OPEX Estimates for caveats regarding the calculation of project CAPEX.
7
Capital intensity has been calculated based on pre-production CAPEX per tonne of Cu, with no accounting for by-product credits (i.e. calculating
on the basis of CuEq).
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Project OPEX
Overall project OPEX has remained unchanged to the August Scoping Study update. A detailed breakdown of project
OPEX is provided as Table 2.
Table 2 OPEX per tonne of ore mined
UNIT OPERATING COSTS UNIT
CATTLE GRID
SOUTH
MG14 WINDABOUT EMMIE BLUFF
Mining A$/t ore 17 40 71 49
Processing – Whole Ore Leach A$/t ore 33 33 33 33
Residual Management A$/t ore 2 2 2 2
General & Administration A$/t ore 4 4 4 4
Total Operating Costs A$/t ore 55 78 110 87
Following review by the Company’s board and management, the Company believes that operating cost estimates are
appropriate for a Scoping Study with a margin of error estimated at +/- 35%.
Coda is currently undertaking a Pre-Feasibility Study into the Elizabeth Creek Project, which will include a detailed
engineering design study intended to produce more up to date and accurate capital cost estimates. OPEX sensitivity
analysis is provided in the “Sensitivity Analysis” section, above
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Mining Production Schedule
Figure 3 The anticipated mined production schedule for all three deposits based on Resource Categorisation. CuEq% for MG14, Windabout and Emmie Bluff is calculated as
per “Metal Equivalents”, above. Mine schedule has been carried over from the December Study with minimal adjustment in order to facilitate comparison between the two
processing options. Coda anticipates that changes to this schedule may occur during mining studies, slated to be undertaken during the PFS if the whole-ore leach flowsheet
is selected. There is a low level of geological confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the
determination of Indicated Mineral Resources or that the production target itself will be realised. Mined production exceeds processing capacity in year 16– excess tonnes will
be stockpiled to maximise plant throughput in year 17.
0.00%
0.50%
1.00%
1.50%
2.00%
2.50%
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
3,500,000
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18
Mined Production by Mineral Resource Category, Elizabeth Creek
MG14 - Indicated Emmie Bluff - Indicated Emmie Bluff - Inferred
Windabout - Indicated Cattle Grid South - Inferred Inferred CuEq Grade %
Indicated CuEq Grade % Cattle Grid South - (Inferred), Cu Grade %
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Table 3 The anticipated mined production schedule for all four deposits based on Resource Categorisation. CuEq% equations for MG14/Windabout and Emmie Bluff are
provided in the Metal Equivalents section, above. There is a low level of geological confidence associated with Inferred Mineral Resources and there is no certainty that
further exploration work will result in the determination of Indicated Mineral Resources or that the production target itself will be realised. Please note that only revenue
from copper, silver and zinc is considered in this Scoping Study.
`
Year
1
Year
2
Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18
MG14 (Indicated), Tonnes - - 1,256,905 - - - - - - - - - - - - - - -
Windabout (Indicated),
Tonnes
- - 847,329 2,368,673 422,132 131,750 - - - -
790,500 985,957 412,591
Emmie Bluff (Indicated),
Tonnes
- - 19,803 777,674 2,600,156 2,910,363 2,911,250 2,820,654 2,815,323 2,773,940 2,758,291 2,721,593 2,663,927 2,615,340 1,285,951 521,342 - -
Emmie Bluff (Inferred),
Tonnes
- - - - 21,076 3,193 - - - 6,841 70,736 49,080 272,193 201,322 972,198 15,994 - -
Cattle Grid South (Inferred),
Tonnes
- - - - - - - - - - - - - - - 1,808,359 1,567,974 666,667
Inferred Mined (Tonnage
basis, %, yearly)
- - 0.00% 0.00% 0.69% 0.10% 0.00% 0.00% 0.00% 0.25% 2.50% 1.77% 9.27% 7.15% 43.05% 58.17% 61.39% 61.77%
Inferred Mined (Tonnage
basis, %, cumulatively)
- - 0.00% 0.00% 0.05% 0.06% 0.06% 0.06% 0.06% 0.07% 0.24% 0.35% 0.98% 1.45% 3.71% 7.94% 11.58% 13.13%
Inferred Mined (Contained
Metal basis, %, yearly)
0.00% 0.00% 0.33% 0.04% 0.00% 0.00% 0.00% 0.13% 1.18% 0.82% 5.26% 4.65% 34.96% 27.46% 36.08% 40.54%
Inferred Mined (Contained
Metal basis, %, cumulatively)
- - 0.00% 0.00% 0.03% 0.03% 0.03% 0.03% 0.03% 0.04% 0.11% 0.16% 0.51% 0.77% 2.43% 3.49% 4.77% 5.42%
Indicated Mined (Tonnage
basis, %, yearly)
- - 100.00% 100.00% 99.31% 99.90% 100.00% 100.00% 100.00% 99.75% 97.50% 98.23% 90.73% 92.85% 56.95% 41.83% 38.61% 38.23%
Indicated Mined (Tonnage
basis, %, cumulatively)
- - 4.93% 12.24% 19.26% 26.32% 33.08% 39.63% 46.17% 52.61% 59.01% 65.33% 71.52% 77.59% 80.57% 83.62% 85.91% 86.87%
Indicated Mined (Contained
Metal basis, %, yearly)
- - 100.00% 100.00% 99.67% 99.96% 100.00% 100.00% 100.00% 99.87% 98.82% 99.18% 94.74% 95.35% 65.04% 72.54% 63.92% 59.46%
Indicated Mined (Contained
Metal basis, %, cumulatively)
- - 5.61% 13.39% 21.22% 29.75% 38.86% 46.89% 54.54% 61.49% 67.78% 73.83% 80.07% 85.47% 88.55% 91.36% 93.62% 94.58%
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Annual Cashflow
Figure 4 Pre-Tax annual cashflow for the base case scenario, Elizabeth Creek Copper-Cobalt Project.
-1,000
-500
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
-400
-300
-200
-100
0
100
200
300
400
500
600
Year
1
Year
2
Year
3
Year
4
Year
5
Year
6
Year
7
Year
8
Year
9
Year
10
Year
11
Year
12
Year
13
Year
14
Year
15
Year
16
Year
17
Year
18
Cumulative
Cashflow
(A$M)
Annual
Cashflow
(A$M)
Pre-Tax Annual Cash Flow (A$M)
E: info@codaminerals.com
ABN 49 625 763 957
6 Altona Street, West Perth
Western Australia, 6005
Taxation
The base case financial analysis is undertaken on a pre-tax basis to reflect the Project’s value at the point of FID
independent of its ownership structure. Accounting for the impact of tax, the financial performance of the Project
changes as follows:
NET REVENUE A$M 8,979
NET CASH FLOW (POST-TAX) A$M 2,841
POST-TAX NPV7 A$M 1,521
POST-TAX IRR % 43%
CAPITALPAYBACK
PERIOD33F33F33F33
F17F
8
YEARS 2.50
It is anticipated that the Project will contribute a total of approximately $313 million in state royalties and $1,198
million in federal taxes over its lifetime.
PROJECT FUNDING
Coda will progress project funding options and ownership structures during the Pre-Feasibility study.
The funding of greenfield mining projects is well understood and a globally common occurrence with multiple
precedent transactions of similar scale and size.
It is currently envisaged that the project may be funded through a combination of equity, project debt, build-own-
operate (BOO) models, and offtake prepayments.
No binding funding commitments have been entered into and there is no certainty that any funding will be secured
on acceptable terms or at all.
FUNDING OPTIONS – DEBT AND EQUITY
Global capital markets provide multiple opportunities for funding of copper and battery minerals projects through
debt and equity.
Coda has received and continues to receive, considerable interest from parties including private equity groups, end
users, and traders of both copper and cobalt materials. Ongoing global efforts to de-carbonise mean that it is likely
that there will be ongoing interest and liquidity for funding of copper and battery minerals projects by global capital
markets.
STRATEGIC PARTNERS – SOURCES OF FUNDING
Coda is actively engaging with multiple potential strategic partners and has established a detailed project dataroom
containing full details of this Scoping Study as well as other relevant project and exploration data. Potential strategic